A 750 MW power station is burning diesel overnight at Kurri Kurri. That is what final commissioning looks like.

Snowy Hydro says final testing runs the station on back-up diesel, overnight, one generator at a time, for about four weeks from 16 July, with a visible plume and odour. Its own page also says the impacts of recent testing are under investigation. The licence caps the plant at 1,100 hours a year, and it is arriving in the weakest quarter for gas generation since 1999.

28 July 2026

Generation + projects

Singleton Council commented twice and backed it the third time. Its HVO submission puts closure at $4.8 billion

Comment-only submissions in 2023 and 2024, formal support in July 2026. The council models refusal at 2,984 jobs and $4.795 billion of output in Singleton alone.

30 August 2026

Generation + projects

Muswellbrook finished Australia’s first pilot 2G biorefinery. The market study commissioned for it says the fuel market is shrinking

Built on budget in a coal town. NSW has legislated a 6 per cent ethanol minimum since 2011 and delivered 2.1 per cent in 2024, down from 2.3. Both SAF projects that would use the output are in Queensland.

30 August 2026

Generation + projects

The decision on mining Hunter Valley Operations to 2042 and 2045 has slipped

Submissions closed 5 August. On 27 August the Commission asked the applicant for more information and requested an extension of time. The outcome is pending.

28 August 2026

Generation + projects

The Tomago deal is a generation deal. It underpins nearly 3 gigawatts of new build

The $2.5 billion package was reported as a jobs story. Read as an energy document it commits to nearly 3 GW of new renewable generation and firming, a demand-response programme at Australia's largest single electricity user, and turns on a contract expiring 31 December 2028.

25 August 2026

Networks + transmission

If a transmission line crosses your land, there is a payment on top of the compensation

$200,000 in 2022 dollars per kilometre hosted, paid annually for 20 years and indexed, separate from and additional to the easement compensation. The Hunter Transmission Project is declared eligible infrastructure.

Networks + transmission

486 businesses can help build the Hunter’s transmission. Fifty of them can manufacture it

The first public count of who here can actually supply the build: 399 capability entries for services, 108 for supply, 50 for manufacturing, and the three components ICN says the region has a real case to make.

16 August 2026

Market + rules

If your power keeps going out, Ausgrid may owe you money. Here is the threshold

20 hours or 10 interruptions in a financial year triggers a payment, and there is a higher tier above it. The catches are real, and Ausgrid’s own two pages state the claim deadline two different ways.

23 August 2026

Market + rules

AEMO’s first reliability run on Eraring’s 2029 date finds no gap. It counts 26 GW of projects that are not committed

The 2026 ESOO says no reliability instrument is needed for 2027-28 or 2029-30. It also says the assessment included about 26 GW of anticipated projects, that without them New South Wales would have triggered a T-3 instrument for 2029-30, and that the T-1 fallback for that year is now closed.

Market + rules

All three NSW networks pushed back on the ring-fencing rule change. Only Ausgrid is arguing about kerbs

We read the Package 1 submissions from Ausgrid, Endeavour and Essential Energy side by side. None supports the Nexa rule change, in three different registers. Ausgrid raises kerbside charging 48 times and wants to fix the overnight home charge problem; Essential, covering 95 per cent of the state, does not raise it once.

26 August 2026

Market + rules

The rules that set the biggest part of your power bill are under review, and submissions close 24 September

Network costs are the largest component of a power bill, on the AEMC's own account. Package 2 asks whether the revenue process is efficient, whether the incentives point the right way, and who carries the risk.

20 August 2026

Market + rules

The energy regulator names its priorities a year ahead. We checked all five against what it did

One produced enforcement, one produced court proceedings, and three produced review and monitoring. The annual check is also becoming a two-yearly one.

Market + rules

Three of the biggest retailers, one Centrepay problem

AGL, Alinta and Origin all appear in the energy regulator’s new compliance report over the same obligation, and it is the one protecting customers who pay their power bill from Centrelink deductions.

10 August 2026

Market + rules

The incentive that made transmission companies mind the wholesale price has been suspended

Version 6 of the AER’s service target scheme drops the Market Impact Component, which priced the wholesale cost of a network’s outages. A working group reports a replacement by late 2026, the same window the Hunter connects its REZ and batteries.

5 August 2026

Market + rules

The five-year decision on what Transgrid can charge has started. Three parties made a submission

The AER opened the reset that sets Transgrid’s allowed revenue from July 2028. The first consultation drew no submissions at all; the second drew three, one of them from Transgrid.

4 August 2026

Generation + projects

Two offers in four days: Origin puts a $150 million number on Eraring’s coal

Origin’s two public offers, the $50 million a year gap it says sits between the parties, and the Fair Work Commission application now hanging over the transition.

18 July 2026

Networks + transmission

Stage 1 of the Hunter’s renewable energy zone network is finished. Here is what was actually built

Fibre optics linking three Upper Hunter switching stations, 350 MW of an eventual gigawatt, and 40 GW of commercial interest queued behind it.

18 July 2026

Market + rules

AEMO’s paperwork carries two Eraring closure dates. Its modelling is calmer than the talk

The 2025 outlook still models August 2027; the current plan uses April 2029. Either way, the operator forecasts no NSW supply gap at the exit.

18 July 2026

Local data

Bayswater and Eraring are running less, not breaking down more

AEMO’s quarterly tables show both Hunter coal stations more available and less used. The squeeze is the market, not the machinery.

18 July 2026

Local data

Eleven months, 10,072 home batteries: the Hunter’s install data, postcode by postcode

The Regulator’s workbooks, charted: the battery boom month by month, and why Maitland’s 2320 leads every count in the region.

18 July 2026

Generation + projects

Liddell’s stacks are down, and the battery replacing them is due about now

The demolition, the $750 million battery at the edge of AGL’s own stated window, and the second 500 MW build already committed at Tomago.

18 July 2026

Networks + transmission

Four transmission projects will shape the Hunter grid’s next decade. Exactly one is committed

Committed, actionable, anticipated, optional: AEMO’s status ladder for the wires being planned through Bayswater, Olney and the zone.

18 July 2026

Generation + projects

The Eraring battery has quietly become a four-stage, 3,160 megawatt hour build

Origin’s own stage table, charted: the megawatts stayed at 700 while the hours deepened from two toward six.

18 July 2026