Generation + projects
Snowy Hydro says final testing runs the station on back-up
diesel, overnight, one generator at a time, for about four weeks from 16 July,
with a visible plume and odour. Its own page also says the impacts of recent testing
are under investigation. The licence caps the plant at 1,100 hours a year, and it is
arriving in the weakest quarter for gas generation since 1999. Updated 3 October: the
diesel phase stalled, restarted on 1 September, and Snowy Hydro’s calendar shows
nothing planned after 1 October.
28 July 2026
Generation + projects
Ausgrid’s 150 MW battery at its Berkeley Vale substation is on exhibition to 10 December. At Steel River, Mayfield West, Ausgrid offered City of Newcastle $150 per MWh a year for 20 years, $936,000 up front, though the state guideline did not require it. The Berkeley Vale EIS names no rate: a grants scheme is still being developed.
17 November 2026
Generation + projects
The agency advice on the 550 MW data centre at Loxford is public. Ausgrid’s letter is not confirmation of network capacity, Hunter Water’s advice rests on dry cooling, the EPA asks about the power station next door, and 671 of 759 submissions object. The applicant has two months to answer.
14 November 2026
Generation + projects
Edify’s 750 MW battery at McCullys Gap offers the NSW guideline rate, about $225,000 a year, against the $200 the council resolved and the McCullys Gap battery next door offers. Its traffic study left out both neighbouring batteries. Submissions close Tuesday 8 December.
11 November 2026
Generation + projects
Bloomfield would build a new 4.1 km section west of the current road near Camberwell over 16 to 20 months, with the old road open until it is finished. The Falbrook Pit would restart around the clock, 10 more landowners gain acquisition rights for noise, and two final voids remain. Submissions closed Tuesday 10 November.
8 November 2026
Generation + projects
AirTrunk’s AI training facility at Loxford would average 458.1 MW at full capacity, against 484 MW for all NSW data centres in the September quarter. Its renewable supply is not yet contracted, and the documents do not define who gets the $200 bill credit for neighbours, or how many. Submissions closed Wednesday 11 November.
5 November 2026
Local data
Utilisation rose at Bayswater (78 to 81 per cent) and Eraring (82 to 86) while availability fell. NSW coal output dropped 252 MW as grid demand fell 202 MW, the reverse of the first half of 2026.
28 October 2026
Networks + transmission
Camp 1 at Inglewood Road, Muscle Creek, or a late alternative on the New England Highway that will be fully assessed only after submissions close on 26 November. The EIS’s social study puts Muswellbrook first, and longest, for combined construction workforce pressure.
22 October 2026
Networks + transmission
EnergyCo’s own pages: two valuations, at least six months to agree, the last 20 per cent of the permanent easement once the line is built and surveyed, and a separate benefit payment after it is switched on. Fewer than 20 private properties are directly affected.
16 October 2026
Networks + transmission
The transmission lines to Bayswater are on exhibition until 26 November. The equine reports expect startled horses, not harm; the anthrax assessment, done from a desk, says a modest livestock risk stays near Rouchel. The breeding-season protections are recommendations, not yet conditions.
15 October 2026
Generation + projects
A 400 MW / 1,600 MWh battery near Muswellbrook. Its own traffic report models highway queues past the right-turn lane when trains close the level crossing, without the 750 MW Bells Mountain or the Gelston battery in the count. The EIS proposes about $320,000 a year for the community.
10 October 2026
Generation + projects
The stockpile about 1 km from Eraring goes from 100,000 to 400,000 tonnes, on the conditions the planning department recommended. The Commonwealth environment minister still decides under the EPBC Act. Origin says Eraring runs to 30 April 2029; the consent runs to 2045.
9 October 2026
Networks + transmission
Who would pay access fees under the July proposal and who would not, how big the pool of projects may be, and where the timetable stands. Projects with an offer to connect when a scheme is declared would pay nothing in.
8 October 2026
Generation + projects
The planning department agreed to OX2 building it in stages. Trucks use Muscle Creek Road only for now, no batteries can be delivered until a fire safety study is approved, and none of the documents we read dates the northern section.
8 October 2026
Networks + transmission
The council wanted worker housing that stays and becomes something else. The site is leased from AGL; the approval limits the camp to the project’s workers, close to what the council asked, and requires the camps decommissioned within 12 months of the project commencing operations.
7 October 2026
Generation + projects
Its draft would have required offsetting of mining emissions above a sector-linked allowance, annual renewable matching and export limits tied to buyers meeting their targets. The consents carry the department’s versions.
7 October 2026
Generation + projects
The scoping report is on the planning portal. The site would go from 700 to about 1,200 MW against 2,880 MW of coal; a determination is expected by mid-2028, then two to three years to build. Origin’s documents give its storage as 4,000 and about 4,942 MWh.
5 October 2026
Networks + transmission
A shock absorber that lets the existing grid carry more, now at full capacity. EnergyCo said in August 2025 the rest would be online that year; it came in September 2026.
3 October 2026
Generation + projects
Against a diesel window of 31 August to 9 September, the schedule marks diesel on two
days. The last three dates are gas, and every other day of October is marked no planned
testing.
30 September 2026
Generation + projects
Comment-only submissions in 2023 and 2024, formal support in July 2026. The council models
refusal at 2,984 jobs and $4.795 billion of output in Singleton alone.
30 August 2026
Generation + projects
Built on budget in a coal town. NSW has legislated a 6 per cent ethanol minimum since
2011 and delivered 2.1 per cent in 2024, down from 2.3. Both SAF projects that would use
the output are in Queensland.
30 August 2026
Generation + projects
Submissions closed 5 August. On 27 August the Commission asked the applicant for more
information and requested an extension of time. The outcome is pending.
28 August 2026
Market + rules
39 to 54 per cent of a DMO price is the wires, not the electrons. The AER sets it for
five years at a time, and on the last NSW transmission reset the number of public
submissions at the opening step was zero. Ausgrid’s next one starts in October.
Generation + projects
The $2.5 billion package was reported as a jobs story. Read as an energy document it
commits to nearly 3 GW of new renewable generation and firming, a demand-response
programme at Australia's largest single electricity user, and turns on a contract
expiring 31 December 2028.
25 August 2026
Networks + transmission
$200,000 in 2022 dollars per kilometre hosted, paid annually for 20 years and
indexed, separate from and additional to the easement compensation. The Hunter
Transmission Project is declared eligible infrastructure.
Networks + transmission
The first public count of who here can actually supply the build: 399 capability
entries for services, 108 for supply, 50 for manufacturing, and the three components
ICN says the region has a real case to make.
16 August 2026
Market + rules
20 hours or 10 interruptions in a financial year triggers a payment, and there is a
higher tier above it. The catches are real, and Ausgrid’s own two pages state the
claim deadline two different ways.
23 August 2026
Market + rules
The 2026 ESOO says no reliability instrument is needed for 2027-28 or 2029-30. It also
says the assessment included about 26 GW of anticipated projects, that without them New
South Wales would have triggered a T-3 instrument for 2029-30, and that the T-1 fallback
for that year is now closed.
Market + rules
We read the Package 1 submissions from Ausgrid, Endeavour and Essential Energy side by
side. None supports the Nexa rule change, in three different registers. Ausgrid raises
kerbside charging 48 times and wants to fix the overnight home charge problem; Essential,
covering 95 per cent of the state, does not raise it once.
26 August 2026
Market + rules
Network costs are the largest component of a power bill, on the AEMC's own account.
Package 2 asks whether the revenue process is efficient, whether the incentives point
the right way, and who carries the risk.
20 August 2026
Market + rules
One produced enforcement, one produced court proceedings, and three produced review
and monitoring. The annual check is also becoming a two-yearly one.
Market + rules
AGL, Alinta and Origin all appear in the energy regulator’s new compliance
report over the same obligation, and it is the one protecting customers who pay their
power bill from Centrelink deductions.
10 August 2026
Market + rules
Version 6 of the AER’s service target scheme drops the Market Impact Component,
which priced the wholesale cost of a network’s outages. A working group reports a
replacement by late 2026, the same window the Hunter connects its REZ and batteries.
5 August 2026
Market + rules
The AER opened the reset that sets Transgrid’s allowed revenue from July 2028.
The first consultation drew no submissions at all; the second drew three, one of them
from Transgrid.
4 August 2026
Generation + projects
Origin’s two public offers, the $50 million a year gap it said sat between
the parties, the March supply agreement that followed, and the Fair Work Commission
application still hanging over the transition.
18 July 2026
Networks + transmission
Fibre optics linking three Upper Hunter switching stations, 350 MW of an
eventual gigawatt, and 40 GW of commercial interest queued behind it.
18 July 2026
Market + rules
The 2025 outlook modelled August 2027; the plan and the 2026 outlook use April
2029. Either way, the operator forecasts no NSW supply gap at the exit.
18 July 2026