The Connection Point. Energy in the Hunter.

Generation + projects

A 750 MW power station is burning diesel overnight at Kurri Kurri. That is what final commissioning looks like.

Snowy Hydro says final testing runs the station on back-up diesel, overnight, one generator at a time, for about four weeks from 16 July, with a visible plume and odour. Its own page also says the impacts of recent testing are under investigation. The licence caps the plant at 1,100 hours a year, and it is arriving in the weakest quarter for gas generation since 1999. Updated 3 October: the diesel phase stalled, restarted on 1 September, and Snowy Hydro’s calendar shows nothing planned after 1 October.

28 July 2026

Generation + projects

Ausgrid offered Newcastle $150 per MWh a year for Steel River. Berkeley Vale’s community scheme is still being developed

Ausgrid’s 150 MW battery at its Berkeley Vale substation is on exhibition to 10 December. At Steel River, Mayfield West, Ausgrid offered City of Newcastle $150 per MWh a year for 20 years, $936,000 up front, though the state guideline did not require it. The Berkeley Vale EIS names no rate: a grants scheme is still being developed.

17 November 2026

Generation + projects

Kurri Kurri data centre: Cessnock council objects, and Ausgrid says the grid connection is not yet approved

The agency advice on the 550 MW data centre at Loxford is public. Ausgrid’s letter is not confirmation of network capacity, Hunter Water’s advice rests on dry cooling, the EPA asks about the power station next door, and 671 of 759 submissions object. The applicant has two months to answer.

14 November 2026

Generation + projects

Bells Mountain battery on Sandy Creek Road offers $150 per MWh a year, not the $200 Muswellbrook council set

Edify’s 750 MW battery at McCullys Gap offers the NSW guideline rate, about $225,000 a year, against the $200 the council resolved and the McCullys Gap battery next door offers. Its traffic study left out both neighbouring batteries. Submissions close Tuesday 8 December.

11 November 2026

Generation + projects

Four km of the New England Highway would move west under a plan to mine Rix’s Creek North to 2049

Bloomfield would build a new 4.1 km section west of the current road near Camberwell over 16 to 20 months, with the old road open until it is finished. The Falbrook Pit would restart around the clock, 10 more landowners gain acquisition rights for noise, and two final voids remain. Submissions closed Tuesday 10 November.

8 November 2026

Generation + projects

A 550 MW data centre is proposed at the old Kurri Kurri smelter. At full capacity its average load would be nearly as much as all NSW data centres together drew last quarter

AirTrunk’s AI training facility at Loxford would average 458.1 MW at full capacity, against 484 MW for all NSW data centres in the September quarter. Its renewable supply is not yet contracted, and the documents do not define who gets the $200 bill credit for neighbours, or how many. Submissions closed Wednesday 11 November.

5 November 2026

Local data

Bayswater and Eraring ran harder in the September quarter, on less available plant. NSW coal fell because the grid needed less, not because coal was outbid

Utilisation rose at Bayswater (78 to 81 per cent) and Eraring (82 to 86) while availability fell. NSW coal output dropped 252 MW as grid demand fell 202 MW, the reverse of the first half of 2026.

28 October 2026

Networks + transmission

The New England transmission line plans a 320-person worker camp east of Muswellbrook, the town its own study expects to carry the longest worker surge

Camp 1 at Inglewood Road, Muscle Creek, or a late alternative on the New England Highway that will be fully assessed only after submissions close on 26 November. The EIS’s social study puts Muswellbrook first, and longest, for combined construction workforce pressure.

22 October 2026

Networks + transmission

Hunter line landholders get 80 per cent of the easement value within 20 business days of the deal, and the rest after construction

EnergyCo’s own pages: two valuations, at least six months to agree, the last 20 per cent of the permanent easement once the line is built and surveyed, and a separate benefit payment after it is switched on. Fewer than 20 private properties are directly affected.

16 October 2026

Networks + transmission

New England REZ line EIS: Upper Hunter horse studs face temporary construction disruption, and a modest anthrax risk remains at Rouchel

The transmission lines to Bayswater are on exhibition until 26 November. The equine reports expect startled horses, not harm; the anthrax assessment, done from a desk, says a modest livestock risk stays near Rouchel. The breeding-season protections are recommendations, not yet conditions.

15 October 2026

Generation + projects

McCullys Gap battery’s traffic study models four other developments expected to use Sandy Creek Road, not the neighbouring Bells Mountain and Gelston batteries; submissions closed 13 October

A 400 MW / 1,600 MWh battery near Muswellbrook. Its own traffic report models highway queues past the right-turn lane when trains close the level crossing, without the 750 MW Bells Mountain or the Gelston battery in the count. The EIS proposes about $320,000 a year for the community.

10 October 2026

Generation + projects

The Independent Planning Commission approved Centennial’s fourfold Cooranbong coal stockpile extension on 29 October; the economic assessment behind it is based on the simplifying assumption of all sales exported

The stockpile about 1 km from Eraring goes from 100,000 to 400,000 tonnes, on the conditions the planning department recommended. The Commonwealth environment minister still decides under the EPBC Act. Origin says Eraring runs to 30 April 2029; the consent runs to 2045.

9 October 2026

Networks + transmission

Hunter councils want a REZ community fund. EnergyCo’s proposed access scheme would have new projects connecting at 132 kV and above contribute to one benefit-sharing program, and a draft it indicated for Q3 had not appeared by 8 October

Who would pay access fees under the July proposal and who would not, how big the pool of projects may be, and where the timetable stands. Projects with an offer to connect when a scheme is declared would pay nothing in.

8 October 2026

Generation + projects

Muswellbrook’s solar farm is being built south first. No work in the north until Sandy Creek Road is upgraded

The planning department agreed to OX2 building it in stages. Trucks use Muscle Creek Road only for now, no batteries can be delivered until a fire safety study is approved, and none of the documents we read dates the northern section.

8 October 2026

Networks + transmission

Muswellbrook objected to the transmission line’s Hebden Road worker camp. The approval requires it decommissioned

The council wanted worker housing that stays and becomes something else. The site is leased from AGL; the approval limits the camp to the project’s workers, close to what the council asked, and requires the camps decommissioned within 12 months of the project commencing operations.

7 October 2026

Generation + projects

Before approving HVO, the planning commission drafted its own emissions conditions. On the department’s advice, it dropped them as drafted

Its draft would have required offsetting of mining emissions above a sector-linked allowance, annual renewable matching and export limits tied to buyers meeting their targets. The consents carry the department’s versions.

7 October 2026

Generation + projects

Origin has lodged plans for a 500 MW, eight-hour battery at Eraring. On its own timetable it would arrive after the coal units close

The scoping report is on the planning portal. The site would go from 700 to about 1,200 MW against 2,880 MW of coal; a determination is expected by mid-2028, then two to three years to build. Origin’s documents give its storage as 4,000 and about 4,942 MWh.

5 October 2026

Networks + transmission

The Waratah Super Battery is at full capacity. What it is for, and why the second half took nine months longer

A shock absorber that lets the existing grid carry more, now at full capacity. EnergyCo said in August 2025 the rest would be online that year; it came in September 2026.

3 October 2026

Generation + projects

Kurri Kurri’s overnight testing calendar has one date left on it, and nothing at all in October

Against a diesel window of 31 August to 9 September, the schedule marks diesel on two days. The last three dates are gas, and every other day of October is marked no planned testing.

30 September 2026

Generation + projects

Singleton Council commented twice and backed it the third time. Its HVO submission puts closure at $4.8 billion

Comment-only submissions in 2023 and 2024, formal support in July 2026. The council models refusal at 2,984 jobs and $4.795 billion of output in Singleton alone.

30 August 2026

Generation + projects

Muswellbrook finished Australia’s first pilot 2G biorefinery. The market study commissioned for it says the fuel market is shrinking

Built on budget in a coal town. NSW has legislated a 6 per cent ethanol minimum since 2011 and delivered 2.1 per cent in 2024, down from 2.3. Both SAF projects that would use the output are in Queensland.

30 August 2026

Generation + projects

The decision on mining Hunter Valley Operations to 2042 and 2045 has slipped

Submissions closed 5 August. On 27 August the Commission asked the applicant for more information and requested an extension of time. The outcome is pending.

28 August 2026

Generation + projects

The Tomago deal is a generation deal. It underpins nearly 3 gigawatts of new build

The $2.5 billion package was reported as a jobs story. Read as an energy document it commits to nearly 3 GW of new renewable generation and firming, a demand-response programme at Australia's largest single electricity user, and turns on a contract expiring 31 December 2028.

25 August 2026

Networks + transmission

If a transmission line crosses your land, there is a payment on top of the compensation

$200,000 in 2022 dollars per kilometre hosted, paid annually for 20 years and indexed, separate from and additional to the easement compensation. The Hunter Transmission Project is declared eligible infrastructure.

Networks + transmission

486 businesses can help build the Hunter’s transmission. Fifty of them can manufacture it

The first public count of who here can actually supply the build: 399 capability entries for services, 108 for supply, 50 for manufacturing, and the three components ICN says the region has a real case to make.

16 August 2026

Market + rules

If your power keeps going out, Ausgrid may owe you money. Here is the threshold

20 hours or 10 interruptions in a financial year triggers a payment, and there is a higher tier above it. The catches are real, and Ausgrid’s own two pages state the claim deadline two different ways.

23 August 2026

Market + rules

AEMO’s first reliability run on Eraring’s 2029 date finds no gap. It counts 26 GW of projects that are not committed

The 2026 ESOO says no reliability instrument is needed for 2027-28 or 2029-30. It also says the assessment included about 26 GW of anticipated projects, that without them New South Wales would have triggered a T-3 instrument for 2029-30, and that the T-1 fallback for that year is now closed.

Market + rules

All three NSW networks pushed back on the ring-fencing rule change. Only Ausgrid is arguing about kerbs

We read the Package 1 submissions from Ausgrid, Endeavour and Essential Energy side by side. None supports the Nexa rule change, in three different registers. Ausgrid raises kerbside charging 48 times and wants to fix the overnight home charge problem; Essential, covering 95 per cent of the state, does not raise it once.

26 August 2026

Market + rules

The rules that set the biggest part of your power bill are under review, and the AEMC is asking who carries the risk

Network costs are the largest component of a power bill, on the AEMC's own account. Package 2 asks whether the revenue process is efficient, whether the incentives point the right way, and who carries the risk.

20 August 2026

Market + rules

The energy regulator names its priorities a year ahead. We checked all five against what it did

One produced enforcement, one produced court proceedings, and three produced review and monitoring. The annual check is also becoming a two-yearly one.

Market + rules

Three of the biggest retailers, one Centrepay problem

AGL, Alinta and Origin all appear in the energy regulator’s new compliance report over the same obligation, and it is the one protecting customers who pay their power bill from Centrelink deductions.

10 August 2026

Market + rules

The incentive that made transmission companies mind the wholesale price has been suspended

Version 6 of the AER’s service target scheme drops the Market Impact Component, which priced the wholesale cost of a network’s outages. A working group reports a replacement by late 2026, the same window the Hunter connects its REZ and batteries.

5 August 2026

Market + rules

The five-year decision on what Transgrid can charge has started. Three parties made a submission

The AER opened the reset that sets Transgrid’s allowed revenue from July 2028. The first consultation drew no submissions at all; the second drew three, one of them from Transgrid.

4 August 2026

Generation + projects

Two offers in four days: Origin puts a $150 million number on Eraring’s coal

Origin’s two public offers, the $50 million a year gap it said sat between the parties, the March supply agreement that followed, and the Fair Work Commission application still hanging over the transition.

18 July 2026

Networks + transmission

Stage 1 of the Hunter’s renewable energy zone network is finished. Here is what was actually built

Fibre optics linking three Upper Hunter switching stations, 350 MW of an eventual gigawatt, and 40 GW of commercial interest queued behind it.

18 July 2026

Market + rules

AEMO’s paperwork carried two Eraring closure dates. Its modelling is calmer than the talk

The 2025 outlook modelled August 2027; the plan and the 2026 outlook use April 2029. Either way, the operator forecasts no NSW supply gap at the exit.

18 July 2026

Local data

Bayswater and Eraring are running less, not breaking down more

AEMO’s quarterly tables show both Hunter coal stations more available and less used. The squeeze is the market, not the machinery.

18 July 2026

Local data

Fifteen months, 13,927 home batteries: the Hunter’s install data, postcode by postcode

The Regulator’s workbooks, charted: the battery boom month by month, and why Maitland’s 2320 leads every count in the region.

18 July 2026

Generation + projects

Liddell’s stacks are down, and the battery replacing them has been commercially available since June

The demolition, the 500 MW battery AGL now says became commercially available in June, and the second 500 MW build already committed at Tomago.

18 July 2026

Networks + transmission

Four transmission projects will shape the Hunter grid’s next decade. Exactly one is committed

Committed, actionable, anticipated, optional: AEMO’s status ladder for the wires being planned through Bayswater, Olney and the zone.

18 July 2026

Generation + projects

The Eraring battery has quietly become a four-stage, 3,160 megawatt hour build

Origin’s own stage table, charted: the megawatts stayed at 700 while the hours deepened from two toward six.

18 July 2026

How this site works

We read the primary documents end to end, link every claim to the source we actually read, and date every figure. The writing is AI-produced under human editorial direction, and we say so plainly. Check our method, and our sources.