The Department of Planning, Housing and Infrastructure’s
exhibition
notice describes the proposal as the 24/7 operation of an approved industrial building as a data centre with a total power consumption of 550.5 megawatts
,
with six diesel generators, lithium-ion batteries, a switchyard and two substations. The
building itself was approved separately, through a complying development certificate. The
application and EIS were on exhibition from 14 October until Wednesday
11 November 2026.
We read the notice, the EIS (prepared by Willowtree Planning, final version dated 28 September 2026), its greenhouse gas, social impact and cost appendices, and the draft planning agreement offer, all posted on the project’s register page. For a Hunter reader, the useful questions are how big this load is, what the grid is being asked to do, and how firm the renewable promise is.
What is proposed
The applicant on the forms is ADW Johnson Pty Ltd. The
draft
planning agreement offer to Cessnock City Council, dated 30 September 2026, is from
AirTrunk Operating Pty Ltd and refers to AirTrunk’s proposed Kurri Kurri Data Centre
. The site is
Lot 4 on Hart Road, part of the former Hydro Aluminium smelter. The EIS lists the Kurri
Kurri Power Station, Snowy Hydro’s 750 MW gas-fired peaker, as the neighbour to
the north.
The Kurri Kurri Data Centre, as its documents describe it
Application SSD-128819490, on exhibition 14 October to 11 November 2026.
- Peak demand550.5 MW: 352.4 MW of computing, 165.6 MW of cooling, 32.5 MW of other plant and losses (EIS Table 9)
- Average use4,013,362 MWh a year at full capacity, an average load of 458.1 MW; 3,612,052 MWh in the ramp-up case the assessment adopts
- ConnectionTwo new overhead feeders from the existing Ausgrid 132 kV line on the south-western boundary into an on-site switching station; four 300 MVA supplies, any two of which run the site
- Back-upSix 2.0 MW diesel generators (12 MW) for critical network equipment only; six minutes of battery back-up for the computing load
- CoolingAir-cooled chillers; no water used for cooling
- Cost$3,775,341,634 excluding GST (estimated development cost)
- JobsUp to 1,210 construction workers at peak, about 470 on average over 14 months; up to 254 operational staff
- TimingElectrical works 2027; energisation and 24/7 operation from 2028, which the EIS calls indicative
How big is 550 MW here
The headline figure is a worst case: the EIS says Table 9 assumes everything runs at
maximum design capacity at once. The better measure is the greenhouse assessment’s
average, an average site load of 458.1 MW
at full capacity. AEMO’s
Quarterly
Energy Dynamics for the September quarter says NSW data centre demand
averaged 484 MW (+40% year-on-year)
,
and that NSW operational demand averaged 7,927 MW. On those figures, this one building
at full capacity would use about 95 per cent as much as every data centre in the state did
in that quarter, and the equivalent of about 6 per cent of the state’s average
operational demand. That is a large new customer on a regional line.
Average power, in megawatts
Bars to scale; the full width is 550 MW.
What the grid is asked to do
The EIS says an Ausgrid connection planning study confirmed the connection would be made
at 132 kV with a switching station on the site, and that the works sought are only the
lead-in from the existing line: no augmentation of the transmission network is proposed
.
It says the site is outside the Sydney Ring
,
where it expects available grid capacity to limit the need for upstream upgrades, and that
arrangements protecting other customers from stranded-asset risk are expected to be incorporated into the connection contracts currently being finalised
.
Those contracts are not among the exhibited documents.
Two design choices bear on the network. The first is a 150 MW flexible load component
that the EIS says can be reduced or shifted for two hours at times of system stress,
without recourse to diesel generation
.
The second is how little back-up it carries. The EIS says the diesel generators cover
critical network equipment, not the computers, and that the batteries hold the computing
and cooling load for six minutes to enable safe shutdown or continuous cooling
. It explains why:
This reflects the intended use primarily as an AI training facility, where the loads are less uptime-critical than a traditional data centre
.
The generators also involve the neighbour. The EIS says routine generator testing will, where reasonably practicable, be scheduled to avoid periods when the Hunter Power Project next door is running on diesel or at peak, through coordination with its operator. Snowy Hydro’s own diesel commissioning at that station is the subject of our earlier reporting.
The renewable promise, and what is signed
The EIS says the company has committed to 100% renewable energy matching by 2030
,
through power purchase agreements, certificates and a program for tenants, and that it is
talking to renewable developers in the Hunter and across NSW. The greenhouse assessment, in
Appendix 14, is more cautious about the same measure. It calls renewable procurement
the largest measure and the least advanced in delivery
,
and says no power purchase agreement is reflected in its results. Against the NSW Data Centre
Guidelines’ seven requirements for renewable supply (Measure 13), it answers five,
including the test of whether the supply is new generation, with To be demonstrated at procurement
,
and on tenants it says No operator or major tenant agreement is demonstrated at the date of this assessment
.
Without that supply counted, the assessment puts peak-year scope 2 emissions, those from
the grid electricity it buys, at 1,999,305 tonnes of CO2-e at full capacity and
1,513,908 tonnes in the ramp-up case. It says the procurement would take market-based
scope 2 to nil from 2030, against a location-based scope 2 of approximately 1.1 Mt CO2-e in that year
.
What Kurri Kurri would get
The draft offer to the council is a contribution of 1 per cent of the estimated
development cost, the amount the council’s section 7.12 plan would levy, conditional on
AirTrunk’s receipt of SSD approval on acceptable terms
and the start of development. On the $3,775,341,634 cost estimate that is about
$37.8 million. It names a Loxford district sporting facility and community facility as
possible uses. The EIS and social impact assessment also describe a community energy program
built around a community battery, through Origin Energy, under which eligible local households
would receive a $200 annual deduction to a standard electricity bill
.
The social impact assessment says that approach is being developed through a partnership agreement currently being finalised
;
it says neighbours and Kurri Kurri residents could take part, but we found no eligibility
boundary or household count in the documents we read.
How we read the documents
The exhibition list at the NSW Planning Portal, filtered to projects on exhibition, was read on 5 November 2026. The project’s documents are listed under “EIS” and “Notice of Exhibition” on its register page; the list loads only in a browser, and each document then downloads by plain request. We read the EIS main volume, Appendices 2, 14 and 22, the notice and the draft planning agreement offer. We did not read the other EIS appendices or the SEARs documents in full. The AEMO figures are from the New South Wales paragraph of its Q3 2026 Quarterly Energy Dynamics. Arithmetic: 458.1 ÷ 484 = 0.946; 458.1 ÷ 7,927 = 0.058; 1 per cent of $3,775,341,634 = $37,753,416; bar widths are each figure ÷ 550.5. “Not contracted” in the standfirst is our summary of the greenhouse assessment’s statements that no power purchase agreement is reflected and no operator or major tenant agreement is demonstrated. We did not contact AirTrunk, ADW Johnson, Ausgrid, the council or the department.
Our read
This section is opinion, based on the facts and documents above.
The load is concrete; the protections are promises. The documents are precise about what this building would draw, down to the tenth of a megawatt. They are much less precise about the two things that decide what it means for everyone else on the grid: the connection contract that is meant to keep stranded-asset costs off other customers, which is not exhibited, and the renewable supply that is meant to cover its use, which its own greenhouse assessment says is the least advanced measure. Neither is a reason to refuse a data centre on a remediated smelter site that is zoned for industry. Both are reasons for the department to make them conditions with dates, rather than leave them as commitments in an EIS.
The design trade is worth naming. Fewer diesel generators means less fuel and fewer emissions at Loxford, and it is a fair choice for AI training. It also means the computing load has six minutes of battery, which the EIS says is to enable safe shutdown, rather than diesel to ride through a supply failure. For the grid that is a large load that could step away quickly, which network planners will want to understand well before 2028.
The $200 is the least defined part. A bill credit for neighbours is the benefit Kurri Kurri residents will notice first, and the documents give no eligibility boundary or household count. Both belong in writing before determination.
We will read the agency advice, including anything from Ausgrid, Transgrid or the council, when it is posted to the register page after submissions close, and report what it says about the connection and the renewable supply.
Updated 14 November 2026. The agency advice is now posted. Cessnock City Council objects; Ausgrid says its letter is not connection approval or confirmation of available network capacity; Hunter Water’s advice relies on the dry cooling design; no letter from Transgrid is among the six. We reported what each says here. On the renewable supply, only the EPA’s general appendix touches it, encouraging measures such as green power purchase agreements; no letter addresses this project’s procurement.
Submissions
Updated 12 November 2026. The exhibition closed on Wednesday 11 November 2026; the project’s register page read on 11 November still gave the exhibition as 14/10/2026 to 11/11/2026, with no extension. Submissions went through that page and are published. We changed the summary, the standfirst, this section and the front-page and Generation cards to the past tense, and dropped two lines inviting submissions.
The notice names the consent authority as the Minister for Planning and Public Spaces or the Independent Planning Commission.
Our earlier reporting on who pays to connect data centres in NSW is here.