Updated 8 November 2026. The Bill received assent on 23 October 2026 and is now the Electricity Infrastructure Investment Amendment Act 2026 (No 41). The consultation page has also changed: it now says the government has passed the Bill, and the condition we quoted from it is gone. The section on the condition is updated to match. No submissions had been published by 8 November.
Updated 18 October 2026. The first version said we could not establish where the Electricity Infrastructure Investment Amendment Bill 2026 was up to, because the NSW legislation website refused us. We have now read it there: the Bill passed both Houses on 14 October 2026, with one amendment in each House. The section on the condition is rewritten, and two new sections set out what passed and what changed on the way, with six new sources. The passages we quote from the consultation page were unchanged on 18 October.
We wrote on 28 August 2026 about the state endorsing 15 data centre projects worth $51.9 billion through its investment fast-track. This is the other half of that story, and it is the half with a deadline on it.
The number
The consultation page states the connection queue plainly. Up to 28 GW
of data centre connection requests as at July 2026, of which around 13 GW
is described as being in advanced discussions. The government then supplies its own yardstick
rather than leaving the reader to find one: 13 GW is more than the average daily
electricity demand in NSW
.
Read that against the region this masthead covers. The Hunter's generators, its transmission, and the closure dates that dominate every energy conversation here are all sized against the demand the state actually has. A single new customer class in advanced discussions for more than that, on top of it, is not a marginal change to the planning problem.
Separately, the same page records 20 data centre projects valued at $51.4 billion in the State Significant Development pipeline as at July 2026. That is a different count from the 15 endorsed projects worth $51.9 billion announced in March, because it is a different measure: one is the planning pipeline, the other is the list the Investment Delivery Authority endorsed. They are not in conflict and should not be added together.
What is being proposed, and why it matters to a household bill
The reform sits inside a three part NSW Data Centre Policy Framework: a
set of planning Guidelines, the cost recovery reforms this consultation is about, and
An IPART review to consider the full recovery of costs of water provision to data centre
customers
. Water is a genuine part of this and is being handled elsewhere.
The energy pillar is stated in one sentence:
Pillar 2 will see the NSW Government progress regulatory reforms to ensure the cost of
additional energy infrastructure investment to enable growth in the sector is recovered from
data centre operators, imposing no net costs on households or businesses
. The stated aim
elsewhere on the page is that data centres can be connected and supplied
without increasing electricity prices and risks for households and small businesses
.
Why this lands on a power bill: network charges are not a small residual. On our own reading of the regulator's determinations, the network component is the largest single element of a Default Market Offer price, ahead of wholesale energy. Network build gets recovered from network users over decades. So the question of who is inside the group that pays for a 28 GW connection task is not a technicality, and it is the question this consultation is actually about.
The condition on all of it
When we first read it, the page said the feedback would
inform new regulations intended to be made under the Electricity Infrastructure Investment
Act 2026
, and it made that subject to the Electricity Infrastructure Investment
Amendment Bill 2026 being passed. That condition has since come off the page, which now says
The NSW Government has passed the Electricity Infrastructure Investment Amendment Bill 2026 to enable these reforms
.
That conditional is doing real work and it tends not to survive into summaries. The
protection consulted on is a set of regulations that do not exist yet, and they depend on
a Bill. That Bill has now passed and become law. The NSW legislation website
records it as Passed by both Houses: 14/10/2026
, after amendment in the Legislative
Assembly on 15 September and in the Legislative Council on 13 October. When we read the
record on 18 October 2026 it showed no assent. It now shows
Assent date: 23/10/2026 (2026 No 41)
, and the Bill says the Act
commences on the date of assent to this Act
, so it has been in force since
23 October. One detail on the consultation page is
off: the Act the Bill amends is the Electricity Infrastructure Investment Act 2020, not a
2026 Act.
What Parliament passed
The Bill never uses the words “data centre”. It lets the Minister declare a
new kind of access scheme over the whole or part of the State that proposes to contain large
load infrastructure
, and it defines large load infrastructure as anything with a network
connection capable of transmitting in total 5MW of electricity instantaneously, or a higher
amount of electricity prescribed by the regulations
that also
meets requirements prescribed by the regulations
. Five megawatts is the floor written
into the Bill. Which sites are actually caught above it is left to regulations that have not
been made.
The household protection the consultation described now has words in the Bill as passed. When
the consumer trustee sets the fees for one of these schemes, it must consider, among other
principles, ensuring proponents of large load infrastructure are responsible for the cost
of network infrastructure required to supply large load infrastructure
and
ensuring NSW electricity customers, other than proponents of large load infrastructure,
do not pay the cost of network infrastructure required to supply large load
infrastructure
. Separately, regulations may
require proponents of large load infrastructure to pay the cost of network infrastructure
required to supply large load infrastructure
, either to a network business or into the
electricity infrastructure fund. And before declaring a scheme the Minister must consider
a report from the Secretary about the potential effects of the declaration on electricity
costs for NSW electricity customers
.
Those are principles the trustee must consider, and powers the regulations may use. They point the cost at the operators, but they do not fix an outcome on their own. The outcome will be in the regulations and the fees.
Two changes on the way through
The Legislative Council changed what the fee setter may weigh. The existing Act tells the
consumer trustee to set access scheme fees taking into account
maximising financial value for NSW electricity customers
. As introduced, the Bill
said the trustee must not consider the principle in subsection (1)(a)
when setting
fees for a large load scheme, which would have taken that customer value principle out of
the calculation. Its explanatory note states the exclusion without giving a reason. The
Council’s amendment of 13 October replaced it: the principle stays in, and the trustee
must not consider the financial interests of proponents and operators of large load
infrastructure
when applying it. The Assembly agreed the next day. On the text, the
version that passed is the more protective of other customers: their value is a principle
the trustee must weigh, and the operators’ finances are left out when it does. Both
versions carried the two principles above that point the cost at operators.
The Legislative Assembly made the other change on 15 September, under the heading
Potential retrospective operation of regulations
. A regulation made under the new
provisions may commence on or after 3 March 2026, including on a day that is earlier than
the day the regulation is published on the NSW legislation website
. So the cost recovery
rules that went out for consultation in August can take effect from a date before the
consultation opened. The Bill does not say why 3 March was chosen.
How submissions were put in
Submissions were open from 17 August to 14 September 2026 at 5:00 pm AEST,
by email, with the subject line the page prescribed: the sender's own name, then the name of
the consultation. The department also ran a webinar on 24 August 2026 and has
published the recording and the slides. One thing worth knowing about anything that was sent:
Submissions will be published on this webpage unless confidentiality has been
requested
.
The page now reads Public consultation is closed
, and it gives a link to what
happens next rather than a date for the government's response (consultation page re-read
30 September 2026, 18 October 2026 and 8 November 2026; no submissions had been published on any of those dates).
This is one of the rare energy consultations where the interest of an ordinary customer is easy to state: whether the rules end up recovering this build from the operators causing it. The Bill has passed, in a slightly different form from the one introduced, so what is left to watch is the regulations: which loads they catch above the 5 MW floor, how they set the cost, and whether they reach back toward 3 March. The submissions, which the page says will be published, are the other thing to watch for.
How we did this
Built from the NSW Climate and Energy Action consultation page for the data centre network connection and cost recovery reforms, read on 28 August 2026 and re-read on 30 September 2026, after the consultation closed. Every figure here is the government's own, quoted or attributed: the 28 GW and 13 GW connection figures and the comparison to average daily demand, the 20 projects and $51.4 billion pipeline, the three pillars, the Pillar 2 objective and the consultation dates. The $51.9 billion figure for the 15 endorsed projects is from the March ministerial release we reported on 28 August 2026, and the two figures are described as different measures because they are. We did not read the consultation paper itself, the webinar slides or the NSW Data Centre Guidelines, so nothing here characterises their contents. The first version could not read the NSW legislation register, which returned 403 to a script and to a browser. On 18 October 2026 we read it in an ordinary browser: the Bill’s record, the Bill as introduced with its explanatory note, the amendments made in each House, the version passed by both Houses, and the current Electricity Infrastructure Investment Act 2020. The comparison of the introduced and passed versions is ours, made line by line; the only differences are the two amendments described. We have not read the second reading speeches or the debate, so nothing here says why either House made its change. We have not contacted the department, IPART, any network operator or any data centre proponent. No allegation is made against any party.
Sources
- NSW Climate and Energy Action, Reforms to electricity network connection and cost recovery arrangements for data centres in NSW (consultation page, read 28 August 2026): that submissions close on 14 September 2026 at 5:00 pm AEST and opened on 17 August; the 28 GW of connection requests and about 13 GW in advanced discussions as at July 2026; that 13 GW is more than the average daily electricity demand in NSW; the 20 projects and $51.4 billion in the State Significant Development pipeline as at July 2026; the three pillars of the NSW Data Centre Policy Framework including the IPART water review; the Pillar 2 objective of recovering costs from data centre operators with no net costs on households or businesses; the webinar of 24 August 2026 and its slides; the submission email format; and that the resulting regulations are intended under the Electricity Infrastructure Investment Act 2026 subject to the Electricity Infrastructure Investment Amendment Bill 2026 being passed. Re-read 8 November 2026: the condition is gone, the page says the government has passed the Bill, and no submissions are published.
- NSW legislation website, Electricity Infrastructure Investment Amendment Bill 2026 (Bill record, read 18 October 2026 and again 8 November 2026): the stages from introduction on 5 August 2026 to passing both Houses on 14 October 2026, and assent on 23 October 2026 as 2026 No 41.
- NSW legislation website, the Bill as passed by both Houses (read 18 October 2026): commencement on assent; the large load infrastructure access scheme and its definition, including the 5 MW floor; the fee principles in the new section 26(1A) and (1B); the regulation powers in the new section 27(1); the Secretary’s report on costs; and the transitional clause allowing regulations to commence from 3 March 2026.
- NSW legislation website, the Bill as introduced, with its explanatory note (read 18 October 2026): the original section 26(1B).
- NSW legislation website, amendments made by the Legislative Assembly on 15 September 2026 (read 18 October 2026): the retrospective operation clause.
- NSW legislation website, the Legislative Council’s amendment of 13 October 2026 (read 18 October 2026): the replacement section 26(1B).
- NSW legislation website, Electricity Infrastructure Investment Act 2020 No 44, current version (read 18 October 2026): the existing section 26(1) fee principles.
- Our earlier report, the Investment Delivery Authority's endorsed rounds (28 August 2026), for the 15 endorsed data centre projects worth $51.9 billion, which is sourced there to the NSW ministerial release of 27 March 2026.
- Our explainer on who sets the network part of a power bill, for the network share of a Default Market Offer price and the determination process that recovers network investment.
Spotted an error, or connecting a load and seeing different numbers? Tell us and we will check it against the consultation paper and log the outcome.