Eraring, Bayswater, Liddell and the batteries rising beside them: the Hunter’s generators and their successor projects, reported from the proponents’ own published documents, with every position attributed by name.

Generation + projects

Singleton Council commented twice and backed it the third time. Its HVO submission puts closure at $4.8 billion

Comment-only submissions in 2023 and 2024, formal support in July 2026. The council models refusal at 2,984 jobs and $4.795 billion of output in Singleton alone.

30 August 2026

Generation + projects

Muswellbrook finished Australia’s first pilot 2G biorefinery. The market study commissioned for it says the fuel market is shrinking

Two ARENA reports on the same Upper Hunter project. One says it was built on budget. The other says ethanol content in NSW fuel sales fell to 2.1 per cent against a mandate above 6, and that aviation fuel is now the driver.

30 August 2026

Generation + projects

The decision on mining Hunter Valley Operations to 2042 and 2045 has slipped. The Commission asked for more time on 27 August

The IPC is deciding two applications to continue the HVO North and South open cut mines, about 430 million tonnes of coal running to 2042 and 2045. Submissions closed on 5 August. On 27 August it sought further information and an extension of time.

28 August 2026

Generation + projects

The Tomago deal is a generation deal. It underpins nearly 3 gigawatts of new build

The $2.5 billion package was reported as a jobs story. Read as an energy document it commits to nearly 3 GW of new renewable generation and firming, a demand-response programme at Australia's largest single electricity user, and turns on a contract expiring 31 December 2028.

25 August 2026

Generation + projects

Snowy Hydro says testing issues stopped Kurri Kurri starting on diesel. Its own calendar now shows no testing at all in August

The community updates page moved on 14 August and added a sentence it did not carry before. The schedule beside it marks every day of August as no planned testing, with diesel testing on one generator resuming 31 August. And the schedule is published only as an image, so a screen reader gets none of it.

18 August 2026

Generation + projects

A 750 MW power station is burning diesel overnight at Kurri Kurri. That is what final commissioning looks like.

Snowy Hydro’s own schedule for the final diesel-testing phase, the sentence on its page saying the impacts of recent testing are under investigation, the 1,100-hour licence cap that defines what a peaker is, and the weakest gas quarter since 1999.

28 July 2026

Generation + projects

Two offers in four days: Origin puts a $150 million number on Eraring’s coal

The mine that supplies every tonne Eraring burns is in a live, priced disagreement with the station’s owner, and the workforce machinery is already at the Fair Work Commission.

18 July 2026

Generation + projects

Liddell’s stacks are down, and the battery replacing them is due about now

AGL’s demolition, its $750 million battery at the edge of the company’s own stated commissioning window, and the hub plans behind both.

18 July 2026

Generation + projects

The Eraring battery has quietly become a four-stage, 3,160 megawatt hour build

Origin’s own stage table, charted: half the project operating, half in build, and a clear pattern of buying hours rather than megawatts.

18 July 2026