Generation + projects

The stations, and what is being built on them

Eraring, Bayswater, Liddell and the batteries rising beside them: the Hunter’s generators and their successor projects, reported from the proponents’ own published documents, with every position attributed by name.

Generation + projects

Ausgrid offered Newcastle $150 per MWh a year for Steel River. Berkeley Vale’s community scheme is still being developed

Ausgrid’s 150 MW battery at its Berkeley Vale substation is on exhibition to 10 December. At Steel River, Mayfield West, Ausgrid offered City of Newcastle $150 per MWh a year for 20 years, $936,000 up front, though the state guideline did not require it. The Berkeley Vale EIS names no rate: a grants scheme is still being developed.

17 November 2026

Generation + projects

Kurri Kurri data centre: Cessnock council objects, and Ausgrid says the grid connection is not yet approved

The agency advice on the 550 MW data centre at Loxford is public. Ausgrid’s letter is not confirmation of network capacity, Hunter Water’s advice rests on dry cooling, the EPA asks about the power station next door, and 671 of 759 submissions object. The applicant has two months to answer.

14 November 2026

Generation + projects

Bells Mountain battery on Sandy Creek Road offers $150 per MWh a year, not the $200 Muswellbrook council set

Edify’s 750 MW battery at McCullys Gap offers the NSW guideline rate, about $225,000 a year, against the $200 the council resolved and the McCullys Gap battery next door offers. Its traffic study left out both neighbouring batteries. Submissions close Tuesday 8 December.

11 November 2026

Generation + projects

Four km of the New England Highway would move west under a plan to mine Rix’s Creek North to 2049

Bloomfield would build a new 4.1 km section west of the current road near Camberwell over 16 to 20 months, with the old road open until it is finished. The Falbrook Pit would restart around the clock, 10 more landowners gain acquisition rights for noise, and two final voids remain. Submissions closed Tuesday 10 November.

8 November 2026

Generation + projects

A 550 MW data centre is proposed at the old Kurri Kurri smelter. At full capacity its average load would be nearly as much as all NSW data centres together drew last quarter

AirTrunk’s AI training facility at Loxford would average 458.1 MW at full capacity, against 484 MW for all NSW data centres in the September quarter. Its renewable supply is not yet contracted, and the documents do not define who gets the $200 bill credit for neighbours, or how many. Submissions closed Wednesday 11 November.

5 November 2026

Generation + projects

McCullys Gap battery’s traffic study models four other developments expected to use Sandy Creek Road, not the neighbouring Bells Mountain and Gelston batteries; submissions closed 13 October

A 400 MW / 1,600 MWh battery near Muswellbrook. Its own traffic report models highway queues past the right-turn lane when trains close the level crossing, without the 750 MW Bells Mountain or the Gelston battery in the count. The EIS proposes about $320,000 a year for the community.

10 October 2026

Generation + projects

The Independent Planning Commission approved Centennial’s fourfold Cooranbong coal stockpile extension on 29 October; the economic assessment behind it is based on the simplifying assumption of all sales exported

The stockpile about 1 km from Eraring goes from 100,000 to 400,000 tonnes, on the conditions the planning department recommended. The Commonwealth environment minister still decides under the EPBC Act. Origin says Eraring runs to 30 April 2029; the consent runs to 2045.

9 October 2026

Generation + projects

Muswellbrook’s solar farm is being built south first. No work in the north until Sandy Creek Road is upgraded

The planning department agreed to OX2 building it in stages. Trucks use Muscle Creek Road only for now, no batteries can be delivered until a fire safety study is approved, and none of the documents we read dates the northern section.

8 October 2026

Generation + projects

Before approving HVO, the planning commission drafted its own emissions conditions. On the department’s advice, it dropped them as drafted

Its draft would have required offsetting of mining emissions above a sector-linked allowance, annual renewable matching and export limits tied to buyers meeting their targets. The consents carry the department’s versions.

7 October 2026

Generation + projects

Origin has lodged plans for a 500 MW, eight-hour battery at Eraring. On its own timetable it would arrive after the coal units close

The scoping report is on the planning portal. The site would go from 700 to about 1,200 MW against 2,880 MW of coal; a determination is expected by mid-2028, then two to three years to build. Origin’s documents give its storage as 4,000 and about 4,942 MWh.

5 October 2026

Generation + projects

Kurri Kurri’s overnight testing calendar has one date left on it, and nothing at all in October

Against a diesel window of 31 August to 9 September, the schedule marks diesel on two days. The last three dates are gas, and every other day of October is marked no planned testing.

30 September 2026

Generation + projects

Singleton Council commented twice and backed it the third time. Its HVO submission puts closure at $4.8 billion

Comment-only submissions in 2023 and 2024, formal support in July 2026. The council models refusal at 2,984 jobs and $4.795 billion of output in Singleton alone.

30 August 2026

Generation + projects

Muswellbrook finished Australia’s first pilot 2G biorefinery. The market study commissioned for it says the fuel market is shrinking

Two ARENA reports on the same Upper Hunter project. One says it was built on budget. The other says ethanol content in NSW fuel sales fell to 2.1 per cent against a mandate above 6, and that aviation fuel is now the driver.

30 August 2026

Generation + projects

The decision on mining Hunter Valley Operations to 2042 and 2045 has slipped. The Commission asked for more time on 27 August

The IPC is deciding two applications to continue the HVO North and South open cut mines, about 430 million tonnes of coal running to 2042 and 2045. Submissions closed on 5 August. On 27 August it sought further information and an extension of time.

28 August 2026

Generation + projects

The Tomago deal is a generation deal. It underpins nearly 3 gigawatts of new build

The $2.5 billion package was reported as a jobs story. Read as an energy document it commits to nearly 3 GW of new renewable generation and firming, a demand-response programme at Australia's largest single electricity user, and turns on a contract expiring 31 December 2028.

25 August 2026

Generation + projects

Snowy Hydro says testing issues stopped Kurri Kurri starting on diesel. Its own calendar now shows no testing at all in August

The community updates page moved on 14 August and added a sentence it did not carry before. The schedule beside it marks every day of August as no planned testing, with diesel testing on one generator resuming 31 August. And the schedule is published only as an image, so a screen reader gets none of it.

18 August 2026

Generation + projects

A 750 MW power station is burning diesel overnight at Kurri Kurri. That is what final commissioning looks like.

Snowy Hydro’s own schedule for the final diesel-testing phase, the sentence on its page saying the impacts of recent testing are under investigation, the 1,100-hour licence cap that defines what a peaker is, and the weakest gas quarter since 1999. Updated 3 October: the diesel phase stalled, restarted on 1 September, and nothing is planned after 1 October.

28 July 2026

Generation + projects

Two offers in four days: Origin puts a $150 million number on Eraring’s coal

Origin’s two priced offers for the coal Eraring burns, the March supply deal that followed, and the workforce machinery already at the Fair Work Commission.

18 July 2026

Generation + projects

Liddell’s stacks are down, and the battery replacing them has been commercially available since June

AGL’s demolition, its 500 MW battery, commercially available since June on AGL’s own account, and the hub plans behind both.

18 July 2026

Generation + projects

The Eraring battery has quietly become a four-stage, 3,160 megawatt hour build

Origin’s own stage table, charted: half the project operating, half in build, and a clear pattern of buying hours rather than megawatts.

18 July 2026