Corrected 5 October 2026. We wrote below that 4,445 MW of battery capacity was commissioned in twelve months. AEMO’s report says that capacity commenced initial commissioning between the end of the first quarter of 2025 and the end of the first quarter of 2026, and that those batteries are either fully commissioned or still working through commissioning. The sentence is left as published; this note replaces it.
Updated 5 October 2026. Origin now proposes to break the pattern this piece describes. Its project page says it is seeking NSW planning approval for a further 500 MW battery with eight hours’ storage (500 MW / 4,000 MWh) on 11 hectares beside Batteries 1 and 2. On the page’s account another $1 billion would be invested if it proceeds, Origin planned to lodge a scoping report in September 2026, and a determination is expected by mid-2028. As at 5 October 2026 that scoping report is on the NSW planning portal (SSD-146467238, status Prepare SEARs), and it gives the new battery’s storage differently from Origin’s page; our story sets out both. Built, it would take the site from 700 MW to 1,200 MW. It is a proposal at the start of the approvals process, not a commitment. The same page gives the combined total as 1,200 MW / 8,600 MWh, which is not the sum of the 3,160 MWh in the table below and the 4,000 MWh proposed (7,160 MWh), so we report the parts and not that total. Battery 2 is unchanged: in the final stages of construction and on track for early 2027. The headline describes the approved four-stage build and stands.
Updated 17 October 2026. This supersedes the line above saying the sentence is left as published. The paragraph on AEMO’s Quarterly Energy Dynamics report further down still said 4,445 MW of battery capacity was commissioned in twelve months. It now says that capacity commenced initial commissioning in that period, and that some is fully commissioned and some is still commissioning, in line with the correction above.
Read next: Origin has lodged plans for a 500 MW, eight-hour battery at Eraring, our full account of the proposed expansion, its scoping report and what has to happen before it exists.
Grid batteries are usually announced once and then talked about as if nothing changed. Eraring’s has changed three times since its first stage was committed, and each change is documented in Origin’s own releases, so the growth can be laid out exactly. This is Origin’s table from its 11 December announcement of the fourth stage, condensed for width; figures and dates are as Origin published them:
| Stage | Announced | Est. commercial operation | Outcome, per Origin’s table |
|---|---|---|---|
| Stage 1 | Apr 2023 | End-2025 | 460 MW at roughly two hours’ dispatch (1,070 MWh) |
| Stage 2 | Jul 2024 | Q1 2027 | Additional 240 MW, grid-forming, 4.3 hours (1,030 MWh) |
| Stage 3 | Nov 2024 | End-2025 | Adds 700 MWh to Stage 1, extending it to 460 MW / four hours (1,770 MWh) |
| Stage 4 | Dec 2025 | Q1 2027 | Adds 360 MWh to Stage 2, extending it to 240 MW / 5.8 hours (1,390 MWh) |
Bars run from Origin’s announcement date to its estimated commercial operation date, as stated in the 11 December 2025 release. Solid bars are complete; outlined bars are under construction. “End-2025” and “Q1 2027” are drawn as December 2025 and March 2027.
Two batteries, four stages
On its project
page, Origin now folds the four stages into two plain-English objects.
“Battery 1” is stages 1 and 3 together: 460 MW with 1,770 MWh
of storage, four hours’ dispatch, which the page says is operating in the
National Electricity Market
“Battery 2” is
stages 2 and 4: another 240 MW with about 1,390 MWh, running to 5.8 hours,
under construction and described as on track for the first quarter of 2027. The page
records the practical texture of a live site: Origin has approval for extended
construction hours, Saturday afternoons and Sundays, through to 31 December 2026, to
get energisation, testing and commissioning done.
Battery 2 also carries a technical term worth one plain sentence. A “grid-forming” battery does not just push energy into a live grid; its inverters can help set the grid’s voltage and frequency rhythm the way heavy spinning generators do, which is part of the system-strength service coal units currently provide. On the same site as four of those coal units, that is not an accidental specification.
The pattern: the megawatts stayed, the hours deepened
Look down the table’s outcome column and one pattern carries the story. The
project’s power rating has been 700 MW since the original development
assessment in 2022; every subsequent decision spent money on duration instead. Stage 3
stretched Battery 1 from two hours to four; Stage 4 stretches Battery 2 from 4.3 hours
to 5.8. Origin’s December release put the total at 3,160 MWh, against the
2,800 MWh first assessed, and committed $80 million to the fourth stage, with
equipment from the Finnish group Wärtsilä and construction by Enerven. In the
December release Origin’s then head of energy supply and operations, Greg Jarvis,
called the site the largest approved battery energy storage system in the
Southern Hemisphere.
Duration is the quiet race in the whole market. A two-hour battery shifts the
evening peak; a five-to-six-hour battery starts covering the shoulder of a whole
evening, which is the work a retiring coal unit leaves behind. AEMO’s
latest
Quarterly Energy Dynamics report measured NEM-wide battery discharge averaging
359 MW in the first quarter of 2026, more than three times the level a year
earlier, with grid-scale battery capacity passing 8,000 MW after 4,445 MW
commenced initial commissioning in twelve months (some of it fully commissioned, some still
working through commissioning). Eraring’s build is the Hunter’s share of that
national surge, and on Origin’s
site
transition page it carries a longer meaning: the company calls the battery
the first step in the transition of the Eraring site
ahead of the coal
units’ scheduled April 2029 closure.
One attribution note. Origin’s December quotes are from Greg Jarvis in his role at the time; Origin has since named Andrew Thornton to lead energy supply and operations. The figures above are as published and remain on Origin’s live pages, which we re-read on 18 July 2026.