Market + rules
Up to 28 GW of data centre connection requests as at July 2026, about 13 GW of it in
advanced discussions, which the government says is more than the state’s average daily
demand. It is consulting on recovering the network cost from operators rather than
households. Submissions close 14 September 2026.
Market + rules
The Investment Delivery Authority endorsed 16 projects worth $34.4 billion in March, then
15 data centre projects worth $51.9 billion three weeks later. AGL’s Hunter energy hub
and the Port of Newcastle clean energy precinct are on the list. A third carries the
region’s name and is proposed for Narrabri. Endorsement is not an approval.
Market + rules
Network is 39 to 54 per cent of a Default Market Offer price, ahead of wholesale. Your
retailer does not set it and Ausgrid does not set it alone. The AER does, five years at a
time, and the process for Ausgrid’s 2029-34 period starts on 31 October 2026.
Market + rules
Ausgrid must compensate customers whose supply is interrupted for long enough or often
enough in a financial year. The two tiers and what they pay, the exclusion that catches most
storm outages, and a claim deadline stated two different ways on Ausgrid’s own pages.
Market + rules
Network costs are the largest component of a power bill, on the AEMC's own account. Its
Package 2 consultation paper asks whether the revenue process is efficient, whether the
incentives point the right way, and who carries the risk. Submissions close 24 September.
Market + rules
The AER sets its compliance priorities twelve months in advance and reports against them
in order, which makes the promise checkable. Reading both reports side by side: one priority
produced completed enforcement, one produced live proceedings, and three produced review,
guidance and monitoring.
17 August 2026
Market + rules
The AER’s new compliance report puts AGL, Alinta and Origin under the same
obligation: overcharging customers who pay through Centrelink deductions. AGL was ordered to
pay $25 million, Alinta paid $1.089 million after 15 infringement notices, and the Origin
allegations are before the Federal Court.
10 August 2026
Market + rules
The AER opened the reset that sets Transgrid’s allowed revenue from July 2028.
The first consultation drew no submissions at all; the second drew three, one of them from
Transgrid. The one consumer advocate says the new capex rules could cost NSW consumers.
4 August 2026
Market + rules
The 2025 reliability outlook still models August 2027; the current system plan uses
April 2029. Dated and attributed, the finding survives both: no forecast NSW supply gap
at Eraring’s exit, and the real question is system security.
18 July 2026