Market + rules
Up to 28 GW of data centre connection requests as at July 2026, about 13 GW of it in
advanced discussions, which the government says is more than the state’s average daily
demand. It consulted on recovering the network cost from operators rather than
households, and the Bill behind it passed both Houses on 14 October 2026.
Market + rules
The Investment Delivery Authority endorsed 16 projects worth $34.4 billion in March, then
15 data centre projects worth $51.9 billion three weeks later. AGL’s Hunter energy hub
and the Port of Newcastle clean energy precinct are on the list. A third carries the
region’s name and is proposed for Narrabri. Endorsement is not an approval.
Market + rules
The 2026 Electricity Statement of Opportunities, published in August 2026, is the first ten-year reliability assessment built on Eraring closing in April 2029 rather than 2025. The headline is reassuring: no forecast reliability gap requires AEMO to ask for a reliability instrument, in either the 2027-28 or the 2029-30 window. The paragraph underneath it is the one worth reading. AEMO states that the assessment included about 26 GW of anticipated projects, that without them a T-3 instrument would have been requested in Queensland and New South Wales for 2029-30, and that because none is requested there is no opportunity to ask for a T-1 instrument for that year later.
Market + rules
Network is 39 to 54 per cent of a Default Market Offer price, ahead of wholesale. Your
retailer does not set it and Ausgrid does not set it alone. The AER does, five years at a
time, and the process for Ausgrid’s 2029-34 period starts on 31 October 2026.
Market + rules
The AEMC’s Electricity Network Regulation Review has more than fifty submissions on its first package and, as far as we can find, nobody has written up what any party actually argued. We read the three that matter most here, from Ausgrid, which is the Hunter’s distributor, and from Endeavour Energy and Essential Energy. Two findings. None of the three supports the rule change that would tighten ring-fencing around them, though they decline in three quite different registers. And on kerbside EV charging the gap between them is not a disagreement, it is a silence: Ausgrid raises it 48 times, and Essential Energy, which covers 95 per cent of New South Wales, does not raise it at all.
Market + rules
Ausgrid must compensate customers whose supply is interrupted for long enough or often
enough in a financial year. The two tiers and what they pay, the exclusion that catches most
storm outages, and a claim deadline stated two different ways on Ausgrid’s own pages.
Market + rules
Network costs are the largest component of a power bill, on the AEMC's own account. Its
Package 2 consultation paper asks whether the revenue process is efficient, whether the
incentives point the right way, and who carries the risk. Submissions closed on 24 September.
Market + rules
The AER sets its compliance priorities twelve months in advance and reports against them
in order, which makes the promise checkable. Reading both reports side by side: one priority
produced completed enforcement, one produced live proceedings, and three produced review,
guidance and monitoring.
17 August 2026
Market + rules
The AER’s new compliance report puts AGL, Alinta and Origin under the same
obligation: overcharging customers who pay through Centrelink deductions. AGL’s $25 million
penalty was set aside on appeal in August 2026, with the AER seeking High Court leave; Alinta
paid $1.089 million after 15 infringement notices; and the Origin allegations are before the
Federal Court.
10 August 2026
Market + rules
The AER opened the reset that sets Transgrid’s allowed revenue from July 2028.
The first consultation drew no submissions at all; the second drew three, one of them from
Transgrid. The one consumer advocate says the new capex rules could cost NSW consumers.
4 August 2026
Market + rules
The 2025 reliability outlook modelled August 2027; the system plan and the 2026
outlook use April 2029. The finding holds: no forecast NSW supply gap at Eraring’s
exit, though the 2026 outlook brings the later NSW gap forward to 2030-31.
18 July 2026