The exhibition of the Kurri Kurri Data Centre, application SSD-128819490, closed on
Wednesday 11 November. By Saturday the project’s
register
page had moved to Current Status: Response to Submissions
,
with six letters of agency advice and the public submissions posted. We
reported the proposal on
5 November: an AI training facility on the old Hydro Aluminium smelter site, with an average
load of 458.1 MW at full capacity, nearly as much as every NSW data centre together drew
in the September quarter. We said then we would read the agency advice when it was posted.
This is what it says.
Who advised the department, and the gist
The six letters posted under Agency Advice on the register, read 14 November 2026.
- Cessnock City CouncilObjects, by resolution of 21 October 2026; asks for more on noise, grid demand, jobs and the use of scarce industrial land
- AusgridConnection talks under way; its letter is not connection approval or confirmation of network capacity
- Hunter WaterAdvice relies on the EIS statement that no potable water is used for cooling; any change should come back as a modification
- NSW EPANo licence appears to be needed, so no full technical review; asks how the site relates to the Kurri Kurri Power Station next door
- Fire and Rescue NSWA fire safety study before construction, reviewed by FRNSW
- Development Coordination AuthorityBiodiversity mapping to be redone; effects on the Kurri Sands stewardship site next door to be assessed; bushfire measures supported
Ausgrid: talks under way, nothing approved
The environmental impact statement says the electrical works sought are a dual overhead
connection from the existing Ausgrid 132 kV line on the site boundary, and that
no augmentation of the transmission network is proposed
.
Ausgrid’s
letter
of 11 November confirms that
formal connection discussions are underway with the proponent and its representatives
,
and lists what is still open: detailed design, network impact assessments, protection
requirements, easements, commercial arrangements and any associated augmentation requirements
.
Then it says, in terms:
This submission does not constitute connection approval, confirmation of available network capacity, or acceptance of the final connection design.
A
Exhibit A · from the source
That is the normal position for a network business at this stage, and Ausgrid says the advice is for planning assessment only. It does mean the question the council and many submitters asked, whether the Hunter network can take a load this size without upgrades someone else pays for, is not answered by anything on the register yet. Transgrid, which runs the transmission network above Ausgrid’s, has no letter among the six, and the department’s list of agencies it is still waiting on does not name it.
Cessnock council: an objection, and a request for more
The council’s
submission,
signed by its development services manager on 11 November, carries the resolution of its
ordinary meeting of 21 October: That Council formally objects to State Significant Development Application SSD
for the data centre. The same resolution asks the council to write to the federal Assistant
Minister for Science, Technology and the Digital Economy seeking a national moratorium on
data centre approvals until federal legislation and frameworks are adopted.
On electricity, the council says the EIS does not sufficiently explain the regional network
implications, cumulative effects alongside other proposed data centres and large users,
whether network augmentation will be required
,
and how energy security risks will be managed. It points to the NSW Data Centre Policy
Framework of August 2026, whose second principle it quotes as Impose no net cost to consumers and communities
.
It also asks how the EIS arrived at 254 full-time jobs, and for an economic assessment of
what else the industrial land could have been used for, because it says the
council’s supply of unconstrained employment land is now likely finite.
On noise, the council notes that the low-frequency noise modelling passes the EPA screening
test, and argues that passing does not necessarily mean zero impact
.
It asks what the operator could actually do if monitoring found a problem, given the noise
report’s own statement that further reductions may impact the operation
.
The money in the council letter looks larger than the developer’s offer, and is not.
The council says any planning agreement will be worth not less than $46,118,317.50 including
GST, and that this includes $4,589,559.53 from the separate certificate for the warehouse
building. Take out the warehouse amount and the GST, and what is left is $37,753,416, which is
exactly 1 per cent of the $3,775,341,634 development cost in the EIS: the same
contribution the draft offer proposed. The council adds that it has told the operator that
any community projects should be implemented by itself, above and beyond the planning agreement
.
Water, fire and the power station next door
Hunter
Water opens by saying data centres can present a significant water security risk
.
Its advice is that this one, as designed, does not: the EIS says the 312 chillers are dry and
air-cooled, and the site’s water plan puts potable use at 2.80 ML a year, for staff
amenities. Hunter Water says its assessment and advice are reliant on this fact
.
It also records that the developer has begun high level consultation
about potable and recycled water from the Kurri Kurri and Farley treatment works for potential
cooling and processing. If that leads to supply for cooling, Hunter Water wants the change
assessed as a formal modification, and says the upgrades planned for the industrial precinct
may not provide the capacity to service developments which require high water demand
.
The EPA
says the proposal does not appear to need an environment protection licence, so it
has not undertaken a full technical review
.
It raises one site-specific point. Snowy Hydro’s gas-fired Kurri Kurri Power Station is
next door under its own licence, and the EPA says the EIS does not appear to indicate whether the proposal will have any relationship
with it; if there is any connection, changes could affect the power station’s approved
limits. The only link we found in the EIS is a scheduling one: routine generator testing will,
where reasonably practicable, be scheduled to avoid periods when the adjacent Hunter Power Project is
running on diesel or at peak.
Fire
and Rescue NSW says data centres present special problems of fighting fire
and recommends a fire safety study Prior to construction
,
developed to its satisfaction, then an emergency plan before the site is commissioned. At least
one public submission objected that the study was being left until after approval; on
FRNSW’s wording, it would still come before building work.
The Development
Coordination Authority, dated 13 November, supports the bushfire measures but asks for the
biodiversity report to be redone in part: the Regent Honeyeater and Swift Parrot habitat
polygons must cover all mapped important habitat on the land, and the 24/7 light and noise
effects on the Kurri Sands biodiversity stewardship site, located immediately west of the subject land
,
need assessing, including whether the data centre would conflict with management such as
ecological burning.
759 submissions
Public submissions on the Kurri Kurri Data Centre, by stated position
All 759 on the register at 14 November 2026. Bars to scale; the full width is 759.
The submitters are local. The suburb most often given is Kurri Kurri, on 148 submissions, then Weston on 81, Heddon Greta on 39, Abermain on 32 and Pelaw Main on 30. A word search of the 671 objections finds electricity, power, energy or the grid in 405 of them, noise in 389, water in 281 and fire in 138. Water is the surprise, given the dry cooling design, and it is one Hunter Water’s letter speaks to directly.
What happens next
The department’s
letter
to the applicant of 12 November asks for a submissions report answering the public and the
agencies, and says it should be provided within two months of the date of this letter
,
which is about 12 January 2027. The time until the report arrives does not count towards the
assessment period. It says the department has not yet received responses from the Development Coordination Authority, Transport for NSW and the Marine Coast Estuary and Flood team
;
the authority’s advice arrived the next day. The department will send its own comments
separately.
How we read the documents
We read the project’s register page on 14 November 2026. Its document lists load only in a browser; each letter then downloads by plain request. We read all six letters under Agency Advice and the department’s request for a submissions report in full. The names of the agencies are from the register’s labels and were checked against each letter’s letterhead. The submission count is ours: we fetched every page of the submissions list (38 pages, 759 entries, matching the register’s own total) and counted the position label on each; suburbs are as submitters gave them, counted without regard to capitals. The theme counts are a case-insensitive search of each objection’s published text for word stems (nois; electric, power, grid or energy; water; fire), so a submission that mentions a word in passing is counted. We name no individual submitter. The planning agreement arithmetic: $46,118,317.50 − $4,589,559.53 = $41,528,757.97; ÷ 1.1 = $37,753,416; 1 per cent of $3,775,341,634 = $37,753,416. The two-month date is our arithmetic from the letter’s date. We did not contact AirTrunk, the applicant, Ausgrid, Transgrid, the council or the department.
Our read
This section is opinion, based on the facts and documents above.
The connection is still the open question. The EIS says no transmission augmentation is proposed; Ausgrid says augmentation requirements are still to be worked out, and that its letter is not confirmation of available network capacity. Both can be true at this stage, but a 550 MW customer is exactly the case where the council’s question about who pays for upgrades matters most. The submissions report is the place to put the connection study’s findings on the record, and the department should ask Transgrid directly rather than wait for a letter that is not on its list.
Dry cooling should be a condition, not a design note. Hunter Water’s advice is only as good as the statement that no water is used for cooling, and the same letter says the developer has started talking about water for cooling. Hunter Water’s ask, that any change comes back as a modification, is the right safeguard, and a consent that names the dry cooling system would make it hard to miss.
The council’s figure is the same money. Reported side by side, $46.1 million and $37.8 million look like a dispute. They are one 1 per cent levy, counted with and without GST and a separate warehouse. The real differences between council and developer are about noise, jobs and the grid, and those are what the submissions report has to answer.
We will read the submissions report when it is posted to the register page, and report how it answers Ausgrid’s open items, the council’s network questions and Hunter Water’s cooling condition.
Our earlier reporting on this proposal is here, and on who pays to connect data centres in NSW here.