The Department of Planning, Housing and Infrastructure’s exhibition notice for the Rix’s Creek North Continuation Project (SSD-60774228) names the applicant as Bloomfield Collieries Pty Ltd and puts the application and environmental impact statement on exhibition from 13 October until Tuesday 10 November 2026. The consent authority is the Minister for Planning and Public Spaces or the Independent Planning Commission. The Commonwealth has also declared the project a controlled action under its environment law, so it will be assessed under both.

We read the notice, the project’s register page and the EIS main volume, with its options appendix. The register page listed no submissions when we read it. For a Hunter reader the useful questions are what happens to the highway, and what changes for the people who live around the mine.

The highway

The EIS says The Project will require the realignment of approximately 4 km of the NEH to facilitate the recovery of the coal resource from the Camberwell Pit Mining Area. The new section would be about 4.1 km long, west of the existing road. Its northern end would join the current highway near the McInerney Road intersection, which would be upgraded. The road would be about 90 m shorter, straighter and flatter, and built to suit 110 km/h, but the EIS says it is proposed to retain the existing 100 km/h speed limit.

The realigned New England Highway, as the EIS describes it

EIS section 4.5 and Table 17. The design is conceptual; detailed design follows any approval.

  • LengthAbout 4.1 km, west of the existing road; about 90 m shorter overall
  • Lanes3.5 m lanes each way, a 1.6 m painted median that can later take a barrier, an overtaking lane each way where needed for climbing
  • Shoulders2.5 to 3 m, sized for future dual lanes in both directions
  • SpeedDesigned for 110 km/h; 100 km/h kept
  • Build timeAbout 16 to 20 months for the road and tie-ins, after approval and detailed design; Table 17’s three stages add up to 16 to 20 months
  • Work hoursUp to 24 hours a day, seven days a week, except the noisiest work: 7 am to 6 pm weekdays, 8 am to 1 pm Saturdays
  • JobsAbout 60 extra full-time workers during construction
  • Who consentsSingleton Council as roads authority, with Transport for NSW’s concurrence; Subsidence Advisory NSW as well, because it sits in a mine subsidence district
Sources: Rix’s Creek North Continuation Project EIS, sections 4.5 and 4.8, Table 17 and the approvals table in section 5.

For drivers, the most important sentence is this one: The existing NEH will remain operational until the realignment is fully constructed, except for the tie-in sections at each end, to ensure disruptions to traffic are minimised. At those tie-ins the EIS lists a single-lane closure, lower speed limits and signage as the measures that may be used, to be set out in a construction traffic management plan prepared with Transport for NSW and the council before work starts. It expects construction traffic at peak to be about 1 per cent of daily highway traffic. It gives no year for the work. Mining in the Camberwell Pit moves west only following commissioning of the NEH realignment.

What else changes

The highway is one item in a larger application that would replace the mine’s existing approval, which allows mining until 31 December 2035. The changes a neighbour would notice:

Rix’s Creek North: approved now, and proposed

From the EIS comparison table (section 4.1) and the exhibition notice.

  • Mine lifeTo 2035 now; to 2049 proposed, about 62 million tonnes more run-of-mine coal
  • OutputUp to 6 million tonnes a year now; up to 4.8 million proposed
  • Falbrook PitIn care and maintenance since 2014; proposed to restart, its rate rising from 1.5 to 3.3 million tonnes a year, and to run 24 hours a day, seven days a week instead of 7 am to 10 pm
  • Workforce250 now; about 325 proposed
  • Final landformOne void with a highwall of around 200 m now; two smaller voids, one in each pit, with no highwalls, proposed
  • Coal transportNo change: by rail to the Port of Newcastle
  • Capital cost$515 million or $527 million, depending on which of two approved Camberwell Pit extents is mined
Sources: exhibition notice; EIS executive summary, sections 1, 2.7 and 4.1 comparison table.

Noise. The EIS predicts operating noise above the trigger levels at 62 privately owned homes or properties across its modelled scenarios, and significant residual impacts at 24 of them. Thirteen of those already have acquisition rights under existing approvals. For the rest it says: Eleven new receptors (comprising 10 landowners) will be eligible for rights to voluntary acquisition.A Under NSW policy, that means those landowners could ask the company to buy their land.

Exhibit A · from the source

Rix’s Creek North EIS, executive summary: of the 24 receptors with significant residual noise impacts, thirteen (10 landowners) have existing rights to voluntary acquisition; eleven new receptors (comprising 10 landowners) will be eligible for rights to voluntary acquisition.
Page 10 of the Rix’s Creek North Continuation Project environmental impact statement, the executive summary on noise, read 8 November 2026. Outlined: the receptors newly eligible to have their land bought. Open the PDF at page 10 · Back to the story

Blasting. The mine already has agreements that allow blasting within 500 m of the highway, Stony Creek Road and Middle Falbrook Road, with temporary road closures during blasts when required, and the EIS says the project would keep using road closures where necessary. It predicts ground vibration within criteria at every assessed location, and airblast within criteria provided extra controls are used near sensitive locations.

The voids. The EIS says Two final voids, one within the Camberwell Pit and one within the Falbrook Pit, would remain as part of the post-mining landform. It predicts both will become increasingly saline pit lakes that act as groundwater sinks in perpetuity, with no discharge to surrounding aquifers or streams. The currently approved landform has no final void at Falbrook and a single void with an exposed highwall of around 200 m, which the EIS calls a higher long-term geotechnical and visual impact.

Emissions. The EIS puts the mine’s own annual average scope 1 and 2 emissions at 0.074 to 0.077 million tonnes of CO2-e, and says that Whilst Rix’s Creek Mine is not currently regulated under the Safeguard Mechanism, it will be in the future, and that scope 1 emissions pass 100,000 tonnes in some years. The EIS puts scope 3, mostly the emissions from burning the coal it sells, at about 3.9 million tonnes of CO2-e a year over the life of the project, roughly 50 times the mine’s own.

How we read the documents

The exhibition list at the NSW Planning Portal, filtered to projects on exhibition, was read on 8 November 2026. The project’s documents are listed under “EIS” and “Notice of Exhibition” on its register page; the list loads only in a browser, and each document then downloads by plain request. We read the notice and the EIS main volume (prepared for Bloomfield by Xenith) and the mine options appendix (Appendix E). We did not read the highway design, noise, greenhouse, air quality, water or social appendices in full, so the highway, noise, void and emissions figures above are the EIS main volume’s own account of them. Arithmetic: 3.9 ÷ 0.077 = 51; 3.3 ÷ 1.5 = 2.2. “Near Camberwell” is our description: the EIS puts the northern tie-in at McInerney Road and says views of the new road would be mostly limited to Camberwell Village and motorists. The 16 to 20 months is the EIS’s figure for the road and tie-ins. We did not contact Bloomfield, the council, Transport for NSW or the department.

Our read

This section is opinion, based on the facts and documents above.

The highway plan is the most reader-friendly part of the application. A new road built beside the old one, with traffic kept on the old road until the new one is finished, is how a highway move should be done, and a straighter section with room for dual lanes is a real gain for the Hunter’s main inland road. The gap is the timetable: the EIS gives durations, not dates, and says nothing about how long the tie-in work at each end would disrupt traffic. A submission could reasonably ask for both to be set out in the conditions, with the community told before each tie-in closure.

Around the clock at Falbrook is the change neighbours will feel. A pit in care and maintenance for more than a decade would restart, more than double its approved rate and lose its overnight quiet period. The 10 landowners gaining acquisition rights are the EIS’s own count of who is hit hardest. Anyone near Middle Falbrook Road who is not on that list has a reason to check the noise assessment (Appendix L) before the exhibition closes.

Two voids, forever, is a trade. The EIS argues two smaller voids with no highwalls are better than the approved 200 m wall, and on stability that is plausible. But the Falbrook Pit currently has no final void at all, and the new plan leaves a saline lake there for good. That is a permanent change to the land.

Submissions

Updated 11 November 2026. The exhibition closed on Tuesday 10 November 2026. Submissions went through the project’s register page, where they are published. We changed the summary, the standfirst, this section and the front-page and Generation cards from “submissions close” to the past tense, and dropped a line inviting submissions.

Updated 16 November 2026. Seven agencies have now posted advice on the EIS to the register page, and the project’s status is Response to Submissions. Three of the letters deal with the highway.

Transport for NSW (11 November) says it is unable to properly assess possible impacts of the proposed development on the State road network and its users. It notes that Details relating to the timing of the highway relocation have not been provided, asks for further clarification as to when the relocation of the highway will occur, and wants the items in its own design review register addressed. The EIS gives 16 to 20 months for the road works, after approval and detailed design; the start date is what Transport for NSW is asking for.

Singleton Council (6 November) says the EIS and its design appendix do not establish an agreed allocation of asset responsibilities and financial liabilities, and that the design appendix is a draft report dated December 2023 with March 2021 drawings. It asks for a costed comparison of realigning the highway against keeping it, and says the new road must be legally available, complete and accepted for safe public use before the existing one is closed or mined through.

The EPA (10 November) says the EIS focuses on mining and it is unclear how surface water pollution risks associated with the relocation would be managed, and recommends the department ask for more detail on erosion and sediment control for the road works.

Our view: when the state roads agency says it cannot yet assess the effect on its own highway, the highway is the open question in this application, not a detail. Bloomfield answers the submissions next. We will report what its response says about the highway’s timing and who pays for and owns the new road when it is posted to the register page.