If you live on or drive Sandy Creek Road, east of the New England Highway at
Muswellbrook, the McCullys Gap Battery Energy Storage System is the project on public
exhibition now, and the window closes on Tuesday 13 October 2026. The
Department of Planning, Housing and Infrastructure’s
exhibition
notice says the application and environmental impact statement are on exhibition from
15 September until 13 October, and that a submission must be lodged online through the
NSW Planning Portal before the close of exhibition
. Anyone can make one.
We read the EIS (August 2026, prepared by GHD for the applicant), its traffic and transport report and the council’s written input, and checked the neighbouring battery, pumped hydro and thermal projects on the NSW Major Projects register this morning. The useful thing for a submission is what the traffic report counts, and what it leaves for later.
What is proposed
The applicant is Muswellbrook Pro Unit Holdings Pty Ltd; the EIS’s list of
abbreviations gives BW Group (parent company of the applicant)
. The battery would sit
across 380 and 578 Sandy Creek Road, about six kilometres northeast of Muswellbrook
,
and connect by an 800 metre line to the existing Muswellbrook 330 kV substation. The
EIS says that, Subject to receiving planning approval, the project is expected to be
operational in 2029 and operate for at least 30 years
(p. vii).
The McCullys Gap battery, as the EIS describes it
Application SSD-81555720, on exhibition 15 September to 13 October 2026.
- Size400 MW for four hours: 1,600 MWh
- Where380 and 578 Sandy Creek Road, McCullys Gap, Muswellbrook Shire
- Connection800 m line to the existing Muswellbrook 330 kV substation
- BuildAbout 18 months; a peak of around 150 workers for four to six months
- RunningRemotely operated; up to six personnel for maintenance on a quarterly basis
- ClearingUp to 16.92 ha of native vegetation, including up to 3.66 ha of a Commonwealth-listed critically endangered ecological community; a controlled action under the EPBC Act
- For the community$200/MWh a year, which the EIS puts at about $320,000 a year, CPI-indexed, through a planning agreement with the council
- ExpectedOperational in 2029, subject to approval
Who else is using Sandy Creek Road
The traffic report’s cumulative section lists eight approved and proposed projects
in the vicinity of Sandy Creek Road
that could overlap with this one’s
construction (p. 48). Its numbers come from four of them. The report says
Four developments have been identified as potentially relevant to assessing future
traffic conditions in 2028
, that All four developments are expected to access or
egress their sites via Sandy Creek Road
, and that their published traffic assessments
were used to inform the cumulative traffic modelling
(p. 9). The four are the Muswellbrook
Solar Farm, the approved Muswellbrook battery, the Muswellbrook Bypass and the
Queensland Hunter Gas Pipeline.
The other four are all still preparing their EISs. Of those, the report says A
number of the developments currently at ‘Preparing EIS’ stage, do not have
sufficient available inputs (e.g., peak hour construction volumes, confirmed access routes,
or sequenced programs) to support inclusion in this assessment
(p. 49). Two of them
are the biggest batteries on the road.
Eight projects the traffic report lists around Sandy Creek Road, and which four it modelled
Status and size from each project’s NSW Major Projects register page, read 10 October 2026. Location and planned start are the traffic report’s (Table 7.1), which says it took them from the register. The tags are our reading of the report’s section 2.4.
-
Bells Mountain battery
Not modelled RegisterPrepare EIS.Construction of a 750 MW / 1,500 MW-hour battery and associated infrastructure
; 388 and 408 Sandy Creek Road (SSD-83968208). Traffic reportImmediately southwest, connecting into the Muswellbrook 330 kV substation; planned start 2027 to 2028. -
Gelston battery
Not modelled RegisterPrepare EIS. A batterywith a capacity of approximately 400 MW/1600 MWh
; Sandy Creek Road / Gelston Lane (SSD-104190458). Traffic reportImmediately southwest, connecting into the 330 kV substation; planned start 2027 to 2028. -
Muswellbrook Pumped Hydro
Not modelled RegisterPrepare EIS. A500 megawatt pumped hydro power station
, declared critical state significant infrastructure (SSI-76014961). Traffic reportImmediately south; planned start 2026; the report says its traffic figures are not yet available. -
Muswellbrook Thermal Storage
Not modelled RegisterPrepare EIS. Up to 30 MW thermal, 4.99 MW electrical; Sandy Creek Road (SSD-88560713). Traffic report2.2 km southwest; planned start unknown. -
Muswellbrook battery
Modelled RegisterDetermination;a 150 MW / 300 MWh battery energy storage facility
at 20-24 Sandy Creek Road (SSD-29704663); a modification is in assessment. Traffic report3.9 km southwest; construction expected from Q4 2026, 12 months. -
Muswellbrook Solar Farm
Modelled RegisterDetermination (SSD-46543209); being built in stages (our 8 October report). Traffic report800 m south; construction from 2026. -
Muswellbrook Bypass
Modelled RegisterNot checked; the EIS lists it as approved under Division 5.1 of the planning act. Traffic report4 km southwest; planned start 2027. -
Queensland Hunter Gas Pipeline
Modelled RegisterDetermination (MP06_0286), a 2009 approval per the EIS. Traffic reportImmediately east; planned start unknown.
The report’s reason for still finding no problem is the road’s spare capacity.
Even for the unmodelled projects, it says, significant cumulative impacts are not
expected because the road network, particularly Sandy Creek Road and the New England
Highway (A15)/Sandy Creek Road intersection already demonstrates substantial remaining
capacity
, and the projects without data are expected to generate comparatively low
and intermittent construction traffic along Sandy Creek Road
(p. 49). The EIS
carries the conclusion forward: When considering relevant future projects with available
information online, significant cumulative traffic impacts to the local road network
during construction are not anticipated
(p. 102).
The two documents also disagree on timing. The traffic report’s table gives Bells
Mountain and Gelston planned starts of 2027 to 2028. The EIS’s own cumulative screening
table says construction timing for both is not yet available (Table 20.2, pp. 151
to 152), and adds that there is limited public information available regarding the
Bells Mountain and Gelston BESS projects at the time of writing
(p. 154).
The turn-off and the level crossing
Sandy Creek Road crosses the Main Northern Line about 45 metres east of the highway. The
traffic report counts about 53 to 59 trains a day over the crossing and notes a
potential risk for construction vehicles to queue back onto the New England Highway
(A15)
(p. 40). Today, the EIS says, Sandy Creek Road carries around 38
vehicles
in each of the morning and afternoon peaks (p. 101). At its own
construction peak, the battery would add up to about 78 vehicle trips in each peak hour,
64 of them inbound in the morning (Table 13.1, p. 102). With the four modelled projects,
the report’s summary puts the total at approximately 355 vehicle trips during the
construction peak hour
at the highway intersection (p. ii).
The report then modelled the intersection with the crossing shut for three trains an hour, 3 minutes 43 seconds each, in 2028 (pp. 40 to 42):
Modelled morning-peak queue on the highway’s southern approach while trains close the crossing, 2028
95th percentile queue in metres. Bars to scale; the full width is 300 m. Both scenarios include the four modelled developments; neither includes Bells Mountain or Gelston.
the queues are expected to extend back beyond the right-turn lane on the New England Highway and result in short periods of delays for northbound and southbound vehicles. The report rates the intersection overall at an acceptable level of service in both. The 80 m difference is our arithmetic (266 − 186).
To manage it, the report suggests the contractor get rail timetables from the Australian
Rail Track Corporation, schedule heavy vehicles where practicable
, consider traffic
controllers on the highway during closures, and tell drivers not to queue across the
crossing (p. 42). As at 10 October we did not find those queue measures in the
EIS’s consolidated mitigation table (Appendix C), whose traffic measures commit to a
construction traffic management plan prepared with the council, Transport for NSW and the
rail corporation as relevant
; nor do the queue lengths appear in the EIS’s
traffic chapter, which we searched for them.
What the community would get
In April 2025, council staff sent the department their input on what the EIS should
cover. The
letter
sets out what the council resolved in February 2025 for battery projects: A monetary
contribution of $200/MWh consistent with the planning agreements with other BESS
projects
, plus a set of local commitments (p. 2). The EIS adopts the rate. 1,600 MWh
at $200 is $320,000, our arithmetic, which matches the EIS’s approximately
$320,000 per annum (adjusted)
(p. 133). The rest of the list is a different
picture.
What Muswellbrook asked of battery projects, against what this EIS proposes
Council asks from its letter of 15 April 2025, items 2 and 16; EIS commitments from the main volume, Appendix C and Technical Reports 7 and 11. The tags are our reading.
-
Annual payment
As asked Council asked$200/MWh of installed capacity, every year of operation, indexed to CPI. EIS proposes$200/MWh, about $320,000 a year, CPI-adjusted, through a planning agreement (p. 133). -
How it is spent
Later Council asked10% to council specialist staff, 90% to the Muswellbrook Shire Community Benefit Fund. EIS proposesThrough the Community Benefit Fund; allocation, eligibility and administrationwill be finalised through the planning agreement process
(p. 19). -
Near neighbours
Not found Council askedNeighbourhood benefits as rate rebates for property owners in the direct vicinity. EIS proposesNo rate rebate commitment found in the documents we searched. -
Apprentices
Not found Council askedAt least four shire residents as apprentices or trainees during construction. EIS proposesNo apprentice or trainee number found in the documents we searched. -
Local spending
Partly Council askedA procurement plan with a minimum 5% local target by project value. EIS proposesInformation for local suppliers and a procurement contact on the project website; no target (measure SE2, p. 134). -
Road wear
Later Council askedPavement damage on Sandy Creek Roadaccurately calculated
per project, part-funded through the planning agreement (resolution of 14 May 2024, p. 5). EIS proposesRoad condition surveys before and after, with repairs (T5); contribution arrangementswill be confirmed and finalised following project approval
(Technical Report 7, p. 49).
On worker housing, which the council also raised, the EIS says The project has
committed to avoidance of the private rental market
and that a workforce accommodation
strategy would be prepared with the council before construction (p. xi).
How we read the documents
The EIS, its technical reports and the council’s letter are under
“EIS” and “Agency Advice” on the project’s register page;
the list of documents loads only in a browser, and each document then downloads by
plain request. Page numbers are the documents’ printed numbers. Statuses, sizes and
addresses for the other projects are from their own register pages and the Muswellbrook
Shire project list on 10 October 2026, not from the McCullys Gap documents; where the
EIS describes a neighbour differently (it gives the thermal facility as up to 30
MW
, where the register separates 30 MW thermal from 4.99 MW electrical, and
puts Gelston about 1.6 km west where the traffic report says immediately
southwest), we give the register’s figure and note the other. “Modelled”
means the project is one of the four whose traffic the report says informed its 2028
model (section 2.4). We searched the EIS main volume, Appendix C and Technical Report 11
for the council’s asks by keyword. Arithmetic: 1,600 × $200 = $320,000;
266 − 186 = 80; 750 + 400 = 1,150. We did not contact the applicant, the council or
the department.
Our read
This section is opinion, based on the facts and documents above.
The money is the settled part. The applicant has matched the council’s battery rate. What is left open is everything else on the council’s list, and the place those things get decided is the planning agreement, after approval. A submission that wants rate rebates for neighbours or apprentices written in should ask for them now, as conditions.
The traffic case rests on a judgement where a number is missing. The
report modelled the two batteries it had data for and treats the two it did not as
comparatively low
in traffic. The one battery it did model, at 150 MW, was put at
51 vehicle movements during the morning and afternoon peak hours by its own traffic
assessment, as the report relays it (p. 11). Bells Mountain, at 750 MW, is five times that size, and the report
lists it with a planned start of 2027 to 2028, overlapping the 2028 peak it assumes for this one. We cannot say what its
traffic will be, and neither can the report. That is the point: with the modelled highway
queue already past the right-turn lane before this battery is added, the reasonable ask is
that the department see a cumulative model with Bells Mountain and Gelston in it before
any of them is determined.
How to have your say
Submissions go through the project’s register page (“Make a submission”) and need a Planning Portal account, your name and address, whether you support, object or comment, your reasons, and a declaration of reportable political donations, according to the notice. Submissions are published; you can ask for your name to be withheld. The portal’s customer support line is 1300 305 695. The department’s contact for the project is on the register page.
One more Upper Hunter energy project is on exhibition this week:
Bowmans
Creek Wind Farm Stage 2, a wind farm with up to 21 wind turbines
, until
12 October.