The Department of Planning, Housing and Infrastructure’s exhibition notice for the Berkeley Vale Battery Energy Storage System (SSD-92577210) names the applicant as Ausgrid Operator Partnership and describes the project as the Development of a 150 MW / 300 MWh battery energy storage system with associated infrastructure. The site is 14 Apprentice Drive, Berkeley Vale, in the Central Coast council area. The documents are on exhibition from 12 November until 10 December 2026, and the consent authority is the Minister for Planning and Public Spaces or the Independent Planning Commission.

It is one of eight batteries Ausgrid is putting on its own substation land, and six of the eight are in the Hunter and on the Central Coast. Steel River, at Mayfield West, was approved in March with a community payment attached. Berkeley Vale is the next of the six on the exhibition list, which makes it a test of whether the deal Ausgrid made with Newcastle carries over.

Berkeley Vale battery at a glance

From the exhibition notice and the EIS (prepared by Colliers Urban Planning for Ausgrid, dated 4 November 2026).

  • SizeUp to 150 MW / 300 MWh; a two-hour battery
  • SiteAbout 1.6 ha of vacant land inside Ausgrid’s Berkeley Vale zone substation property, zoned E4 General Industrial
  • ConnectionA 33 kV underground cable into the substation, which Ausgrid is separately upgrading
  • NeighboursNearest homes about 300 m south-east; 63 residential lots within 500 m and 863 within 1 km
  • BuildAbout 22 months, from late 2027 to 2029; 110 full-time-equivalent construction jobs, 3 once operating
  • Cost and lifeAbout $146 million; up to 50 years
Sources: exhibition notice; Berkeley Vale BESS EIS, sections 1.2, 2.1, 2.2.4 (Table 2), 3.2 (Table 4) and 4.2 (Table 7). “Two-hour” is our arithmetic (300 ÷ 150). The receiver counts are the EIS’s, by cadastral lot, not by house.

What Newcastle got for Steel River

Steel River East is Ausgrid’s 200 MW / 400 MWh battery inside its substation at 1 McIntosh Drive, Mayfield West. The Independent Planning Commission approved it on 23 March 2026. Its statement of reasons records the money: The Applicant has offered Newcastle City Council (Council) a Voluntary Planning Agreement (VPA) with an agreed contribution value of $150 per MWh hour generated per annum for 20 years (paid as one upfront payment prior to the commencement of construction), equating to $936,000.A It adds: Council has agreed to this offer.

Exhibit A · from the source

Independent Planning Commission, Steel River East statement of reasons: the applicant has offered Newcastle City Council a voluntary planning agreement with an agreed contribution value of $150 per MWh hour generated per annum for 20 years, paid as one upfront payment before construction, equating to $936,000; council has agreed to this offer.
PDF page 4 of the Independent Planning Commission’s Statement of Reasons for Decision on Steel River East BESS (SSD-77450458), 23 March 2026, read 17 November 2026. Outlined: the rate and term, the lump sum, and the council’s acceptance. Open the PDF at page 4 · Back to the story

It is a condition, not just a promise. Condition A14 of the development consent says: Prior to commencing construction, unless the Planning Secretary agrees otherwise, the Applicant must enter into a VPA with Council on the terms of Ausgrid’s letter of offer of 10 December 2025, reproduced as Appendix 4. That letter explains both numbers. The $936,000 is the value of annuity in real dollars, which is why it is less than 20 years of payments added up. And on the rate, Ausgrid wrote: While this guideline does not apply to BESS on industrial zoned land, the proposed contribution within this VPA is consistent with the rate for BESS across other zonings within NSW.

The guideline it means is the department’s November 2024 Benefit-Sharing Guideline. It applies to batteries where BESS projects are proposed on rural zoned land only and sets their rate at $150 per megawatt hour per annum for stand-alone battery energy storage systems in a rural zone. So at Steel River, Ausgrid offered the rural rate on industrial land without being required to. The department’s assessment report shows how it got there: the council had first Requested monetary contributions under its section 7.12 Development Contributions Plan equivalent to 1% of the estimated cost of the development. The planning agreement came Following further engagement with Council, and Ausgrid’s letter asks that those section 7.11 and 7.12 levies be excluded.

What the Berkeley Vale EIS says instead

The Berkeley Vale site is zoned E4 General Industrial, so the guideline does not reach it either. The EIS says so, then describes something different from Steel River: Ausgrid is developing a community benefit sharing scheme to deliver direct community benefits associated with the BESS program.B The benefit sharing scheme would be delivered through a transparent grants-based process, directly accessible to councils and community organisations and local institutions. It gives no rate, no dollar figure and no term. On the council, it says: Ausgrid is scheduling a meeting with Central Coast Council in Quarter 3 of 2026 to discuss the proposed approach for benefit sharing. The EIS is dated 4 November 2026, after that quarter ended, and does not say whether the meeting happened.

Exhibit B · from the source

Berkeley Vale BESS EIS, Table 3: the Benefit Sharing Guidelines do not apply to BESS on non-rural-zoned land; Ausgrid is developing a community benefit sharing scheme for the BESS program, delivered through a grants-based process; Ausgrid is scheduling a meeting with Central Coast Council in Quarter 3 of 2026 to discuss it.
Page 28 of the Berkeley Vale BESS environmental impact statement (Colliers Urban Planning for Ausgrid, 4 November 2026), Table 3, Strategic Context, read 17 November 2026. Outlined: why the guideline does not apply, what Ausgrid offers instead, and the council meeting. Open the PDF at page 28 · Back to the story

In July 2025 the plan had a different shape. Ausgrid’s scoping report for Berkeley Vale (prepared by AECOM, 22 July 2025) said: Ausgrid will also hold discussions with Central Coast Council in relation to strategic support from Ausgrid for local sustainability and social value opportunities as part of a Voluntary Planning Agreement. We searched the EIS main volume and its community engagement, consultation and social impact appendices (D, G and R) for “planning agreement” and “VPA” and found neither. Central Coast Council’s own letter to the department at the requirements stage, dated 22 September 2025, covers planning controls, engineering and environment; we found no request in it for a payment, a contribution or a planning agreement.

Berkeley Vale’s community offer, scoping report against EIS

The same applicant and site, July 2025 and November 2026. The tags are our reading.

  • Vehicle
    Changed
    Scoping, July 2025Discussions with the council about support “as part of a Voluntary Planning Agreement”. EIS, November 2026A program-wide grants scheme Ausgrid is developing, open to councils, community organisations and local institutions. No planning agreement found.
  • Amount
    Not stated
    Scoping, July 2025None given. EIS, November 2026None given: no rate per MWh, no total, no term.
  • Council
    Pending
    Scoping, July 2025Briefings held with the council, state MP and federal MP through July 2025 (EIS, Table 12). EIS, November 2026A meeting on benefit sharing being scheduled for July to September 2026; outcome not stated.
Sources: Berkeley Vale BESS scoping report, section 2.4; EIS, Table 3 (p. 28) and Table 12 (p. 43). “No planning agreement found” means we searched the text of the EIS main volume and Appendices D, G and R for “planning agreement” and “VPA” on 17 November 2026; we did not read the other appendices.

What the Steel River rate would mean at Berkeley Vale

Nothing in the Berkeley Vale documents commits Ausgrid to the Steel River rate. But it is the only number Ausgrid has put to a council for one of these batteries, and its own letter called it consistent with the state rate. Applied to Berkeley Vale’s 300 MWh, it would be $45,000 a year. Over 20 years that is $900,000 added up, or about $702,000 as a lump sum if it were discounted the way the Steel River figure was.

Two Ausgrid batteries, one rate on the table

Lump-sum community payment, dollars. Bars to scale; the full width is $1,000,000.

Steel River, 400 MWh, as offered and accepted$936,000
Berkeley Vale, 300 MWh, if Ausgrid used the same rateabout $702,000
Berkeley Vale, as the EIS standsno figure
Sources: Steel River East statement of reasons, p. 4, and Ausgrid’s letter of offer of 10 December 2025 (consent Appendix 4); Berkeley Vale BESS EIS, Table 3. The Berkeley Vale figure is our arithmetic and a what-if, not an offer: $936,000 × 300 ÷ 400.

The answer matters past Berkeley Vale. Ausgrid’s battery program page lists eight sites: Steel River at Mayfield West, Homebush, Rothbury, Rathmines, Berkeley Vale, Kurnell, Wyong and Kurri Kurri. It says Once approved, the batteries will be built and operated by PLUS Grid Storage (PLUS GS), a specialist energy storage company, under an agreement with Ausgrid. A program-wide grants scheme would presumably also cover the Rothbury, Rathmines, Wyong and Kurri Kurri batteries when they reach exhibition, and the EIS ties the scheme to the BESS program.

Ausgrid’s eight battery sites

As listed on Ausgrid’s program page, read 17 November 2026. Region and stage are ours, from the planning documents named.

  • Steel River, Mayfield WestNewcastle. Approved by the Commission, 23 March 2026; $150/MWh planning agreement with the council
  • Berkeley ValeCentral Coast. On exhibition, 12 November to 10 December 2026; scheme still being developed
  • Rothbury, Rathmines, Wyong, Kurri KurriHunter and Central Coast. Not on exhibition on 17 November 2026; Ausgrid says sites are at different stages
  • Homebush, KurnellSydney. Outside this site’s patch
Sources: Ausgrid, Grid-Scale Battery Energy Storage Systems page; Steel River East statement of reasons; Berkeley Vale register page and exhibition notice. “Not on exhibition” means none of the four was on the Planning Portal’s list of projects on exhibition on 17 November 2026; we did not check each one’s stage.

How we read the documents

The NSW Planning Portal’s list of projects on exhibition was read on 17 November 2026. The Berkeley Vale document list loads only in a browser; each document then downloads by plain request. We read the exhibition notice, the EIS main volume (version dated 4 November 2026), the scoping report, the council’s requirements-stage letter, and searched Appendices D, G and R. From the Independent Planning Commission’s Steel River East case page we read the statement of reasons, the development consent (including Appendix 4, Ausgrid’s letter of offer, which is an image and was read by eye) and the department’s February 2026 assessment report. Arithmetic: 300 × $150 = $45,000 a year; × 20 = $900,000; Steel River’s undiscounted total is 400 × $150 × 20 = $1,200,000, so its $936,000 lump sum is 78% of that; $936,000 × 300 ÷ 400 = $702,000. The letter gives no discount rate, so the $702,000 is a scaling, not a calculation of our own. We did not contact Ausgrid, PLUS Grid Storage, either council or the department.

Our read

This section is opinion, based on the facts and documents above.

Ausgrid has already shown what it thinks fair, and the Central Coast should ask for the same. At Steel River the state rule did not apply and Ausgrid offered the state rate anyway, by an agreement the Commission then made a condition of consent. That is a good precedent, and Ausgrid set it. At Berkeley Vale the EIS swaps a planning agreement, which the council holds and the consent can enforce, for a grants scheme Ausgrid runs and has not yet described. A grants scheme may turn out as generous, but a reader cannot tell from the EIS, and neither can the department. Asking for a rate, a term and a council agreement in the consent is a fair thing for a submission to do.

The gap is in the guideline, not just this project. The rural-only limit fits batteries on farmland. It leaves out batteries on industrial land beside suburbs, which is where Steel River and Berkeley Vale sit: 863 residential lots lie within a kilometre of the Berkeley Vale site. The two batteries proposed on rural land at McCullys Gap, in the Upper Hunter, offer $150 and $200 per MWh a year. If the department thinks substation batteries should pay too, the guideline should say so, rather than leaving it to each applicant.

Submissions

Submissions close on 10 December 2026 and go through the project’s register page (“Make a submission”), where they are published. The notice says you can ask for your name to be withheld, and that a submission must declare reportable political donations from the last two years.

We will read the agency advice on the EIS, including Central Coast Council’s, when it is posted to the register page after the exhibition, and report what it says about a community payment.