Corrected 11 November 2026. The exhibition has been extended. A Department of Planning extension notice says The exhibition has been extended until Thursday 26 November 2026, and the Major Projects register now gives 15 October to 26 November. This story gave 12 November as the last day for submissions; we missed the extension when it was posted. We have changed the closing date in the summary, standfirst and body. Earlier dated notes are left as written.

Five camps, and the one at the Hunter end

The project is EnergyCo’s dual 500 kV line carrying the New England renewable energy zone’s output to Bayswater Power Station, which we covered when the EIS went on exhibition. Its Traffic and Transport Impact Assessment (Technical Report 7) lists the five proposed camps and their indicative peak capacity in Table 6-3:

  • Camp 1, Inglewood Road, Muswellbrook: 320, serving Bayswater Power Station to north of Aberdeen.
  • Camp 2, Waverley Road, Waverly: 320, serving north of Aberdeen to Pages Creek.
  • Camp 3, in the vicinity of Barry: 320, location subject to confirmation.
  • Camp 4, Oxley Highway, about 15 km west of Walcha: 550.
  • Camp 5, Glenburnie Road, Kentucky, about 15 km south-west of Uralla: 550.

The same report places Camp 1 east of Muswellbrook at the intersection of Muscle Creek Road, Beggary Creek Road, and Inglewood Road (p. 71). Construction is planned to start in 2028 and take about six years, with a peak of about 1,400 workers in late 2030. The traffic report expects about 1,200 of them to live in the camps and about 200 to be local; at that overall peak it models 125 people at Camp 1 (Table 6-11). It also says Camps 1, 2 and 3 would need to come online sooner as they are expected to reach their peaks in 2030.

An alternative not yet fully assessed

The Social Impact Assessment (Technical Report 4) gives Camp 1 two possible homes: Inglewood Road, or a recently identified possible alternative location for Camp 1 (identified as Camp 1 Alternate) on New England Highway, Muswellbrook. It says both the Camp 1 alternative and Camp 3 at Barry have only recently been identified by EnergyCo, and that Full assessment of the proposed locations for Camp 3 and Camp 1 Alternate will be undertaken as part of the Submissions Report/Amendment Report (section 1.2.1.8).

So the site most of the EIS assesses for Camp 1 may not be the one built, and the other candidate will be fully assessed only after public submissions close. The documents we read give no reason for the late alternative; the social study’s overview map (Figure 1.2) marks it only at map scale, as not yet subject to full assessment.

What councils asked for

The social impact study reports that Councils along the alignment have expressed a consistent desire to have workforce accommodation camps located near town centres to improve integration outcomes for local communities in hosting the temporary workforce, and to allow for the infrastructure to be more easily repurposed following the construction period (section 5.2.8.1). It records the wider wish for adaptive long-term re-use of camp facilities, and that housing solutions are outside the scope of the project.

Muswellbrook Shire Council has a written position. Its Temporary Workforce Accommodation Policy, adopted in September 2025, says the council prefers TWA to be within or near existing urban areas and villages and gives preference to proposals with a pathway for permanent conversion (read 7 October 2026). In April 2026 it objected to the Hunter Transmission Project’s camp for up to 300 workers off Hebden Road, which the July approval kept, as we reported. The New England EIS documents we read do not record what Muswellbrook Council thinks of Camp 1, and do not test either Camp 1 site against the council’s policy.

Muswellbrook first, and longest

The social impact study models the combined construction workforce of every relevant project around six service centres, using the list of projects in section 24 of the EIS. For Muswellbrook (Figure 5.16) it says workforce activity is already elevated from 2026, reaches a sustained and pronounced peak between approximately Q2 2029 and Q4 2029, and stays relatively high through 2030. Its conclusion:

Overall, the graph highlights Muswellbrook as experiencing both the earliest onset and longest duration of elevated cumulative workforce demand, with sustained implications for housing, services and infrastructure capacity over multiple years.

On the chart, the tallest bar, for the third quarter of 2029, comes close to 2,000 workers. Most of it is other projects in the study’s list, among them the Muswellbrook Bypass, the Hunter Transmission Project and the Muswellbrook Solar Farm; the New England line’s share grows through 2029. For projects without published construction dates, the study aligned their schedules with this project’s, to represent a ‘worst-case scenario’ cumulative workforce total, so the peak is a planning ceiling, not a forecast. The traffic report puts the Hunter Transmission Project’s own construction at 2027 to 2029, with 830 full-time-equivalent workers at peak and a potential overlap in 2028 and 2029.

On short-term accommodation the study finds limited supply across Scone and Muswellbrook, and counts 170 short-term rooms within an hour of Camp 1, across Muswellbrook, Aberdeen, Scone and Singleton, to house the up to 40 people it assumes will set up each camp over about six months (Table 5.3): 23.5 per cent of them, which the study counts as relatively low demand.

The roads to Camp 1

The traffic report routes Camp 1 traffic from the New England Highway along Muscle Creek Road, Inglewood Road and Beggary Creek Road, and lists upgrades including a basic right turn at Muscle Creek Road and Inglewood Road, sealed widening of up to 2 metres along Inglewood Road, and a basic right turn at the camp access. At the late-2030 peak it estimates 62 vehicle movements a day between Camp 1 and the work sites, 44 light and 18 heavy (Table 6-11).

Our view

This is opinion, built on the documents above. Muswellbrook has already argued once over where a transmission camp should go and what it should leave behind, and the approval kept that camp where EnergyCo proposed it. This EIS reaches the same town with the same question, and its own study says the town is under more sustained workforce pressure than anywhere else on the route. Yet the choice between the two Camp 1 sites, and whether either one leaves anything after construction, is set to be settled in a report that follows the submission period rather than in the document people are being asked to comment on. Anyone with a view on where Camp 1 goes, and what happens to it afterwards, should put it in a submission by 26 November, because the alternative may not be put on exhibition in the same way.

We will report which Camp 1 site EnergyCo puts forward when the Submissions Report is published.

Have your say

Submissions go to the Department of Planning, Housing and Infrastructure through the NSW Major Projects register until Thursday 26 November 2026, extended from 12 November. EnergyCo’s release lists an information session at the Muswellbrook Library Seminar Room on Friday 6 November, 11am to 2pm.

How we read it

We read the camp, workforce, cumulative and accommodation sections of the Social Impact Assessment and the camp, workforce and cumulative sections of the Traffic and Transport Impact Assessment, not either report end to end. The chart reading (close to 2,000 in the third quarter of 2029) is ours, from Figure 5.16, which has no data labels. Capacities are the reports’ “indicative” figures. We have not sought comment from EnergyCo or Muswellbrook Shire Council.