The Hunter Transmission Project,
the 500 kV line from Bayswater to Olney, was approved on 27 July 2026, according to
the NSW
Major Projects register. Part of its construction workforce will sleep in a camp at
the Hebden Road construction support site, which EnergyCo’s
exhibition
fact sheet places at Muswellbrook, up to 300 workers
. The council’s
17
April 2026 letter to the Department of Planning, Housing and Infrastructure says
it has resolved to OBJECT
to the camp, because it will provide poor living
arrangements for workers and minimal positive legacy for Muswellbrook Shire
(p. 1).
The approval kept the camp. Read against the council’s letter, its conditions
give the council some of what it asked for, and not the legacy its policy puts first:
accommodation that stays and becomes housing or visitor accommodation. EnergyCo’s
answer, as the council’s letter reproduces it, is that the site is leased from AGL,
so there would not be an opportunity to repurpose the site once construction is
complete
(p. 5).
What the council asked for, and what the approval says
Muswellbrook adopted a
Temporary
Workforce Accommodation Policy on 23 September 2025, the day before the
project’s exhibition closed. It says the council prefers TWA to be within or near
existing urban areas and villages
, gives preference to proposals with a pathway
for permanent conversion
, supports dry mess facilities to improve safety and encourage use of local hospitality venues
and wants food, laundry and
labour bought locally (sections 4.1 and 4.3). The April letter applies that policy to
the Hebden Road camp, item by item. The
Instrument
of Approval answers in conditions B66 to B73.
Six things Muswellbrook asked for, against the approved conditions
Council requests from its 17 April 2026 letter; conditions from the Instrument of Approval, 27 July 2026. The tags are our reading.
-
Where it goes
Not changed Council askedNoout-of-town camps
, its position since May 2024; it sent EnergyCo a site suitability assessment of alternatives (pp. 1 to 2, 4). Approval saysCampsdescribed in the EIS and in Appendix 1 of this approval
; the EIS camps include Hebden Road (B66, B67). -
What it leaves
Different Council askedIf it stays at Hebden Road, water and wastewater built to permanent standards for a legacy use (comment 4, p. 5). Approval saysAll camps decommissioned and rehabilitated within 12 months of commencing operations, infrastructure removed to 500 mm, unless the Planning Secretary agrees otherwise (B73, Table 1). -
Who sleeps there
As asked Council askedProject construction workers only:Any proposal to accommodate workers from other projects should be prohibited
(comment 6, p. 6). Approval saysCampsmust only be used to accommodate workers associated with construction or road upgrades for the development
(B67). -
Local spending
Partly Council askedLocal procurement targets and a plan showing how they will be met (comment 7, p. 6). Approval saysMeasures tosupport local suppliers in servicing the camp where possible
; no targets (B68(g)). -
Design
Later Council askedAn indicative design before approval (comment 8, p. 6). Approval saysA management plan with site layout, capacity and staging, prepared before constructionin consultation with relevant Council/s
(B68). -
Housing pressure
Partly Council askedA Workforce Accommodation Strategy, with six-month notice of demand and triggers (comment 11, pp. 7 to 8). Approval saysA social impact management plan coveringhousing availability and affordability
, with quarterly public monitoring reports (B71).
The Department’s
assessment
report summarises Muswellbrook’s position (Table 6, p. 27) as having
Requested clarification on the proposed TWA including its location, scale, and
potential impacts on tourism and local services
. We found no reference in the
report to the objection in the council’s April letter. The preceding page (p. 26) says
the Department met Singleton and Cessnock councils during the assessment.
Why the camp stays where it is
The council’s letter quotes EnergyCo’s reply of 24 March 2026 (p. 4).
EnergyCo did a desktop analysis of the 14 sites the council identified; two, both
council-owned, rated medium suitability. Moving the camp, it said, would mean A
modification to planning consent (at a minimum a 4-month delay to the project)
,
Additional cost of approximately $5 million
and Potential social licence issues
with additional community consultation required
. The council disagreed that a
modification would be needed: it says a camp approved through the state’s
construction workers accommodation pathway can serve several projects, and it is not
clear why use of an alternative site would require a modification to the HTP planning
consent
.
On legacy, EnergyCo told the council it is exploring alternative opportunities to
deliver legacy outcomes
, which may include supporting enabling infrastructure (e.g.
roads, electricity, water and sewer) at a Council-identified site
, and that it is
committed to working with Council
(pp. 4 to 5). The council’s reply: it
is yet to see these opportunities clearly defined or progressed
. Nothing in the
approved conditions refers to such an arrangement.
Hebden Road is one of three camps. The figures have moved since exhibition, and
EnergyCo’s
project
page, as at 7 October 2026, still gives the exhibited version: three sites, space
for around 780 workers
.
Camp beds for the Hunter Transmission Project, as exhibited and as assessed
Bars to scale; the full width is 900 beds.
Left to right: Hebden Road, Gouldsville Road, Cooranbong
Left to right: Hebden Road, Freemans Drive, Wollombi Road (new)
Three TWAs for a combined total of up to 900 workers at Hebden Road, Freemans Drive and Wollombi Roadand the new Wollombi Road camp at up to 300 (p. 100); Hebden Road’s 300 is EnergyCo’s figure in the council’s letter (p. 5), and Freemans Drive’s 300 is the fact sheet’s, which together sum to the 900. Singleton Council’s advice quotes EnergyCo: the camp
has been removed from the Gouldsville Road construction support site.
EnergyCo also told the council the camp’s capacity will be further refined by
the appointed construction contractors and will be bound by the lease agreement between
AGL and EnergyCo
(p. 5), and that its design will be subject to the preference
of the design and construct contractor(s) yet to be appointed
(p. 6).
How it got here, and what lands at the same time
The council says it raised the location early and was not heard. EnergyCo’s responses in the same letter describe meetings and ongoing discussions. The dates, as the documents give them:
The Hebden Road camp, from the council’s first objection to construction
- May 2024Council’s submission on the project’s assessment requirements says it does not support
out-of-town camps
. - 27 Aug to 24 Sep 2025Environmental impact statement on exhibition, with the Hebden Road camp for up to 300.
- 23 Sep 2025Council adopts its Temporary Workforce Accommodation Policy.
- 28 Jan 2026Council sends EnergyCo an issues tracker and a site suitability assessment.
- 24 Mar 2026EnergyCo replies: 14 sites assessed, two medium; moving would cost about $5 million and at least four months.
- 17 Apr 2026Council resolves to object to the camp.
- 27 Jul 2026Project approved, camp included, conditions B66 to B73.
- 3 to 18 Sep 2026Council’s own expression of interest for worker accommodation.
- Dec 2026 to Jun 2027Peak construction workforce for the Muswellbrook Solar Farm, per the council’s letter.
- Feb 2027Muswellbrook BESS
looking to commence construction
and the Muswellbrook Bypassplanned to commence construction
, per the council’s letter. - 2027, peak 2028Transmission line construction, about 2.5 years; camps built before major works.
The other projects at the bottom of that list are what the letter keeps returning to. It says that
multiple projects (mining, infrastructure and renewable energy based) are proposing
arrangements that place pressure on both short- and long-term accommodation within the
Muswellbrook Shire
, and that without a coordinated approach unacceptable pressure on
local rental vacancy rates and affordability may arise
(pp. 7 to 8).
The council’s own move
Just over five weeks after the approval, on 3 September, the council
invited
expressions of interest from developers, investors and operators in providing worker
accommodation in the shire. The
EOI
document says the council has identified several strategically located
properties
and describes three models: a tourist park taking up to 50 beds, worker
camps of 150 to 300-plus beds on a build, own, operate, deconstruct model, and 51 to 150
beds of longer-term accommodation for essential workers with Long-term legacy
accommodation outcomes
. It is a non-binding market sounding exercise
and
not a procurement, tender or request for proposal
. It closed on 18 September.
Muswellbrook Shire Council supports TWA that leaves the Shire better off, not accommodation that isolates workers on the edge of town and packs up without a trace
As at 7 October 2026, the council’s worker accommodation news tag listed only the 3 September release, with no published outcome of the expression of interest.
How we read the documents
The council’s letter and Singleton Council’s advice are under
“Agency Advice” on the project’s Major Projects register page, and the
assessment report and Instrument of Approval under “Determination”. Page
numbers for the assessment report are its printed numbers, which run 11 behind the PDF
page index. EnergyCo’s words in this story are as the council’s letter
reproduces them from EnergyCo’s 24 March 2026 email; we have not seen the email
itself. The letter also mentions a meeting with EnergyCo on 12 November 2026
, a
date after the letter itself; we have not used it. The assessment report’s
amended-project table (p. 100) says the Gouldsville Road camp would remain, while
its project description (p. 2) and Singleton Council’s advice put the three
camps at Hebden Road, Freemans Drive and Wollombi Road; we follow p. 2. We searched
the assessment report for every mention of Muswellbrook and of objections to find what
it records of the council’s position. The council’s EOI document is an image
PDF with no text layer; we read it page by page. Arithmetic: 300 + 180 + 300 = 780;
3 × 300 = 900. We did not contact the council, EnergyCo or the Department.
Our read
This section is opinion, based on the facts and documents above.
The approval treats the camp as construction equipment, and the council wants it treated as housing. Both are reasonable. A state approval for one line has to make that line clean up after itself, and EnergyCo does not own the land. But the cost of the gap falls on Muswellbrook, which on the council’s own list has a solar farm, a battery and a highway bypass starting or peaking in the same months. This approval asks the project’s social impact plan to consider cumulative impacts with other State significant projects (B71); it does not, and one project’s approval is a poor tool to, set up a shared accommodation plan for all of them.
The useful next step is a written one. EnergyCo has said it will work with the council on legacy outcomes at a council site. The council says it has not seen them defined. The camp’s management plan is due before construction and has to be prepared with the council; that is the natural place to put whatever is agreed on paper, where the shire can read it.
What to watch next
The accommodation camp management plan and the social impact management plan must be
prepared before construction starts (B68, B71). B71 requires quarterly monitoring reports
to be publicly available on the project website
, which will be the first public
measure of the project’s effect on housing. The other is whatever the council does
with the responses to its expression of interest.