The exhibition of the Rix’s Creek North Continuation Project, application SSD-60774228, closed on Tuesday 10 November. When we read the project’s register page on 16 November it held seven letters of agency advice. By 20 November it held eleven. We reported the proposal on 8 November, and on 16 November added what the advice said about the realigned New England Highway: Transport for NSW said it could not yet assess the effect on the state road network. This is the rest of the advice, read in full.

Who advised the department, and the gist

The eleven documents under Agency Advice on the register, read 16 and 20 November 2026.

  • NSW EPACannot complete its assessment; wants more on greenhouse gas, surface water, groundwater, dust and noise rights
  • DCA Technical AdvisoryGroundwater entitlement short of predicted take; more justification for clearing about 235 ha of native vegetation; heritage and bushfire measures supported
  • NSW ResourcesAn efficient use of the resource; $580 million in royalties; titles in order
  • Resources RegulatorMore on rehabilitation timing and on capping the tailings dams
  • Singleton CouncilOfficers’ submission, not yet considered by the council; wants matters resolved before determination, including the highway
  • Transport for NSWUnable to properly assess the effect on the state road network; asks when the highway would move
  • Department hazards teamAsks whether existing and relocated explosives magazines meet the separation distances in the standard
  • Crown LandsTwo Crown parcels and Crown roads affected; wants a consolidated plan for access, closure and acquisition
  • DPIRD FisheriesNo objection
  • “Transgrid”The letter filed under this label is from Ausgrid: no direct impact on its existing assets identified
Sources: the agency documents linked in the sources list. NSW Resources posted a covering letter and two attachments, which is how eleven documents come from ten advisers.

The EPA: not enough to finish

The EPA’s letter of 10 November is the longest of the eleven, and its opening finding is plain. It has reviewed the EIS and notes it does not provide the information required to allow us to complete our assessment. It lists matters to be addressed before determination under five heads: greenhouse gas, surface water, groundwater, air quality and noise.

One mine or two. Bloomfield’s application covers Rix’s Creek North only; Rix’s Creek South, next door, runs under its own consent. But both mines sit under one environment protection licence, number 3391, and the project would let overburden and reject move between them. The EPA says the greenhouse assessment should cover the whole licensed premises, because the continuation project would not operate as a standalone development but as part of a revised operating regime for the complex. It also asks Bloomfield to Clarify whether the Applicant seeks to retain a combined maximum extraction rate of 6 million tonnes of ROM per annum for the Falbrook and Camberwell pits. The EIS describes the project as cutting the approved peak from 6 to 4.8 million tonnes a year, so the answer matters to what is actually being approved. Singleton Council makes the same point from its side: the transfers between the two mines, it says, requires clarification of the activities authorised under each consent.

On emissions more generally, the EPA says the claim that methane from the coal cannot feasibly be reduced rests on low gas content, but the assessment does not provide the gas content of the areas proposed to be mined. It asks whether Bloomfield has considered emissions goals beyond its Safeguard Mechanism obligations, which the mine will enter, and how the baseline for those obligations was worked out.

Dust near Falbrook. The project would restart the Falbrook Pit, in care and maintenance since 2014, and raise its rate from 1.5 to 3.3 million tonnes a year. The air quality assessment predicts extra days above the 24-hour particle criteria at four receptors, and the EPA singles out one: It is noted that up to 19 additional PM10 (24 hour) exceedances are predicted at receptor N23. Two of the four, N23 and N35, are east and north-east of the project near Falbrook. The assessment’s answer is to pause pit and overburden work when dust is elevated, and with that modelled it predicts no additional exceedances. The EPA’s problem is that the assessment does not say which activities were paused or what would trigger a pause, and that No ambient air monitoring station in proximity to these locations has been identified. It also questions the background dust figures, which were derived by adjusting measured data with modelled data and in places produce negative increments, and the 85 per cent dust control assumed for watering haul roads, where its own figures for watering are 75 and 50 per cent.

Water. A new sediment dam is sized for an 80th percentile five-day storm, where the guideline the EIS cites recommends 90th percentile for disturbance lasting more than three years, and the dam would appear to overflow offsite. The EPA says The use of undersized basins that discharge offsite is likely to increase discharge frequency. It also wants the water quality criteria rebuilt against the national guidelines, the location and contents of out-of-pit waste dumps set out, and a groundwater bore that read about pH 12 from 2017 to 2021 investigated for grout contamination before its data is used as baseline.

Noise rights. The EPA reads the EIS as identifying a further 24 receivers that would qualify for voluntary acquisition and 26 for mitigation under the state policy. Some properties already hold such rights under the existing consent, and the EPA asks Bloomfield to clarify if the receivers that qualify for voluntary acquisition or mitigation rights under the current approval will be carried over, if this application is approved.

Water licences: 139 units short

The Development Coordination Authority’s technical advice, issued 18 November and the last to arrive, brings together the state’s biodiversity, heritage, bushfire and water advisers. Its water section turns on numbers in the project’s own groundwater assessment. Bloomfield holds 300 units of permanent entitlement in the Sydney Basin North Coast Groundwater Source and a further 107 units under a temporary trade that expires on 30 June 2028. The predicted cumulative peak take is about 439 ML a year, in 2031. So, the DCA says, an additional 139 units would be required to cover the predicted cumulative peak take after 2028.A

Exhibit A · from the source

DCA Technical Advisory advice on Rix’s Creek North, 18 November 2026: based on the permanent entitlement identified in the assessment, an additional 139 units would be required to cover the predicted cumulative peak take after 2028.
Page 11 of the DCA Technical Advisory advice on the Rix’s Creek North EIS, issued 18 November 2026, the water section. Outlined: the entitlement the mine would still need after the temporary trade ends. Open the PDF at page 11 · Back to the story

The groundwater assessment says Bloomfield is negotiating with a third party, but the DCA says it does not identify the volume proposed to be obtained, when it would be obtained or the proposed arrangement, and adds: The approach of relying on temporary transfers to account for future water take represents a commercial and compliance risk for the proponent. It wants evidence, before determination, that the extra entitlement can be obtained before the water is taken. It also finds the EIS licensing table inconsistent with the groundwater assessment for the Glennies Creek alluvium and regulated river, a point Singleton Council raises too, and notes the reports cite a water sharing plan that has been repealed.

235 hectares of bush

The DCA’s biodiversity advisers say the project would clear about 235 ha of native vegetation, including 185 ha of threatened ecological communities, most of it in condition that meets the threshold for a critically endangered community under federal law. Their assessment is that The proposed expansion will result in significant residual impacts on biodiversity values. Recorded threatened species include the Squirrel Glider, Brush-tailed Phascogale, Hunter Valley Delma and seven threatened microbats. The biodiversity report says avoidance was taken as far as practicable; the DCA says it gives limited detail on the alternatives considered, and that for the highway in particular the relationship between mining constraints and the resulting road alignment is not clearly explained. It also wants the boundary of the surveyed land reconciled with the pit at the north and west of Camberwell.

On heritage, the DCA broadly agrees with the assessment: the project would affect 25 of 26 Aboriginal sites in the project area, with a scarred tree avoided and protected, and it recommends a cultural heritage management plan as a condition. It supports the bushfire measures.

The case for

NSW Resources’ resource and economic review is the most favourable of the eleven. Using confidential mine schedule data supplied by Bloomfield and its own price assumptions, it estimates total royalties of $580 million in 2026 dollars ($290 million in present value), about $25 million a year, $152 million a year in combined economic benefits, and an average of 244 full-time jobs. Its conclusion: The Project is considered to be an efficient use of resources. Its covering letter confirms Bloomfield holds the titles it needs. The review also records that Rix's Creek South is not part of this approval process.

The rest

The Resources Regulator wants more on how long rehabilitation would take after mining ends and on drying out the tailings dams so they can be capped, and notes it does not provide any endorsement of the proposed rehabilitation methodologies. The department’s hazards specialist, in an email of 17 November, says the EIS mentions moving explosives magazines but that insufficient information was provided to confirm if the location of the existing and relocated explosives magazines are and will comply with the minimum separation distance requirements, including from both the existing and new highway alignments. Crown Lands says two parcels of Crown land, subject to undetermined Aboriginal land claims, and some Crown roads would be affected, and that acquisition of land permanently taken into the pit should be investigated. DPIRD Fisheries raises no objection to the proposal.

Singleton Council’s submission was prepared by its officers to meet the deadline and, it says, has not yet been considered by Council; it is due before the council in early December. Beyond the highway, it asks for a receptor-by-receptor schedule of noise and dust rights, and makes a point that goes to how acquisition rights work in practice: Existing acquisition rights or agreements do not, by themselves, demonstrate acceptable conditions for residents who remain.

What happens next

The department’s letter to Bloomfield of 13 November asks for a submissions report answering the 922 public submissions and says: We also require a response to the issues raised by agencies in their advice. It sets no deadline, and the time until the report arrives does not count towards the assessment period.

How we read the documents

We read the project’s register page on 16 and 20 November 2026. Its document lists load only in a browser; each document then downloads by plain request. We read all eleven documents under Agency Advice and the department’s request for a submissions report in full. The Crown Lands letter is a scanned image with no text layer, so we read it on screen and quote none of it. The agency names are the register’s labels, checked against each letterhead; the document labelled Transgrid is an Ausgrid letter. The EIS figures (the 4.8 million tonne peak, the Falbrook rates, the receptor table) are from the EIS main volume, read 8 November; the 19 days at receptor N23 match its Table 46, the unmitigated case. Arithmetic: 439 − 300 = 139; 300 + 107 = 407, below 439; 107 ÷ 407 = 26 per cent. The water and biodiversity figures are the DCA’s account of the project’s own assessments, which we did not read in full. Receptor IDs are the EIS’s labels for properties; we name no landholder. We asked Bloomfield on 22 November what combined maximum extraction rate it is seeking, and will publish its answer here. We did not contact the council, the agencies or the department.

Our read

This section is opinion, based on the facts and documents above.

The EPA’s complex-wide question is the big one. An application that covers one half of a jointly licensed mine, while moving waste between the halves, invites exactly the question the EPA asks: what changes, in total, if this is approved? Its request to say plainly whether the 6 million tonne combined rate is being kept goes to the headline claim of the project, that output falls. That should be answered in a number, not a description.

Dust controls need a monitor where the dust is. The EIS’s own table has 19 extra days above the PM10 criterion, in a modelled year with no mitigation, at one property near Falbrook, and the revised modelling has none if work is paused at the right moments. That is a reasonable plan only if someone can see the right moments coming. With no monitor near N23 or N35, a consent that relies on pausing work should require one there, with the trigger written down.

Water should be secured before it is taken, not after. The DCA’s ask is modest: show that the missing 139 units can be bought before the mine needs them. More than a quarter of the mine’s current groundwater entitlement in that source is on a temporary trade ending in 2028, and the peak arrives three years later. A condition tying the extra take to entitlement actually held is the obvious answer.

None of this is unusual for a coal mine extension at this stage, and NSW Resources’ numbers show why the state wants it to proceed. The point of the agency round is that the approval is only as good as the questions answered before it. We will read Bloomfield’s submissions report when it is posted to the register page, and report how it answers the EPA on the combined extraction rate and the Falbrook dust monitoring, and the DCA on the groundwater entitlement.

Our earlier reporting on this project, including the highway advice, is here.