Updated 23 November 2026. The department has answered. Asked on 21 November what it advised on whether the Cessnock contributions plan applies to this project, a spokesperson for the Department of Planning, Housing and Infrastructure said, in a reply through our tips form: The proponent, Ausgrid, has committed to providing contributions to Cessnock Council equivalent to the amount set out in the Benefit Sharing-Guideline.
The answer does not say whether the department advised that the council’s section 7.12 plan applies. So what it advised is still not public, and the agency advice on the EIS, including the council’s, is still to come after the exhibition closes on 17 December.
The Department of Planning, Housing and Infrastructure’s
exhibition
notice for the Kurri Kurri Battery Energy Storage System (SSD-113069490) names the applicant as
Ausgrid Operator Partnership, the site as 28 Johnson Avenue, Kurri Kurri, and the proposal as the
Construction, operation and decommissioning of a Battery Energy Storage System with a capacity of 200MW / 800MWh and ancillary infrastructure.
The documents are on exhibition from 19 November until Thursday 17 December 2026.
It is the third of the six Hunter and Central Coast batteries Ausgrid is planning on its own substation land to go on public exhibition, after Steel River at Mayfield West and Berkeley Vale. It is also the biggest of the three by stored energy: 800 MWh, against 400 MWh at Steel River and 300 MWh at Berkeley Vale.
Kurri Kurri battery at a glance
From the exhibition notice and the EIS (prepared by Colliers Urban Planning for Ausgrid, dated 5 November 2026).
- SizeUp to 200 MW / 800 MWh; a four-hour battery
- SiteAbout 1.3 ha of Ausgrid land beside the Kurri Kurri zone substation, zoned E5 Heavy Industrial
- ConnectionA 33 kV underground cable into the substation, where Ausgrid is separately adding a transformer
- NeighboursHomes about 65 m south, across the disused South Maitland railway; a 7.5 m noise barrier on the south-east and south-west sides
- BuildAbout 22 months, early 2028 to late 2029; 50 construction jobs on average, up to 100 at peak; 2 once operating
- Cost and lifeEstimated development cost $247,486,275; up to 25 years
The rate Ausgrid has named
The EIS
(section 5.4, p. 49) says Ausgrid’s grants will follow the state’s rule for batteries on
farmland, although this battery is not on farmland:
The rate of investment will be based on the NSW Benefit- Sharing guidelines, which sets a rate of $150/MWh per year of operation for standalone BESS projects.
A
It calls that rate
a clear and defensible benchmark.
The money would be delivered via targeted grants
,
with its distribution decided in consultation with the council, First Nations groups and the local
community.
At 800 MWh that is $120,000 a year. Over the battery’s life of up to 25 years it adds up to $3,000,000. The EIS gives no term, no indexing and no start date for the payments, and does not say whether they would be fixed in a planning agreement or a condition of consent.
Exhibit A · from the source
That is a change from a week ago. Ausgrid’s
Berkeley
Vale EIS, dated 4 November 2026, one day earlier than Kurri Kurri’s, said only that
Ausgrid is developing a community benefit sharing scheme to deliver direct community benefits associated with the BESS program.
It named no rate. The Kurri Kurri figure matches the one Ausgrid offered City of Newcastle for Steel
River, which the Independent Planning Commission’s
statement
of reasons (p. 4) records as
$150 per MWh hour generated per annum for 20 years (paid as one upfront payment prior to the commencement of construction), equating to $936,000.
The vehicle is different, though. Steel River’s money goes to the council under a planning
agreement. Kurri Kurri’s would be grants Ausgrid administers.
What the council asked for
Cessnock City Council’s
letter
to the department on the draft requirements, dated 16 April 2026, pointed out that the state
guideline does not cover this battery because the land is not rural, and quoted the guideline
itself on what follows from that: such projects
would be subject to standard council rates and contributions based on their land use zoning and any relevant impacts on local infrastructure and services.
Its ask (PDF p. 2) was plain:
It is the expectation of Council that local contributions will be levied in accordance with this Plan.
The plan is the Cessnock S7.12 City Wide Infrastructure Contributions Plan. The council’s
contributions
page says it covers commercial, industrial and government agency development, and sets the levy
at 1% of development cost over $200,000. On this project’s estimated cost that is about
$2.47 million, paid once.
The EIS (Table 13, p. 48) records the request and says Ausgrid and the council have discussed
whether the levy applies,
taking into account advice provided by DPHI.
It does not say what that advice was or whether the council has accepted the grants instead. Its
answer to the council is the grants scheme, with engagement to continue
pending any requirements of the proposed Hunter Central Coast Renewable Energy Zone Access Scheme.
Newcastle went the same way: the department’s assessment of Steel River records that City of
Newcastle first asked for its own 1% section 7.12 levy and settled on the planning agreement.
Two ways to pay Kurri Kurri
Dollars, added up without discounting or indexing. Bars to scale; the full width is $3,000,000.
The scheme nobody has seen yet
The EIS makes the grants second in line (p. 48):
Community benefit sharing for the Project is subject to any benefit sharing requirements under Energy Co’s proposed Hunter-Central Coast Renewable Energy Zone Access Scheme.
Ausgrid’s own scheme applies only if that one does not include benefit sharing (p. 49, Exhibit
A).
That scheme does not exist yet even in draft. EnergyCo’s
July
2026 consultation paper gave an indicative third-quarter 2026 date for a draft declaration. On 21 November its
access
scheme page was still marked “Updated 28 July 2026” and still said
Later in the year, we'll seek feedback on the proposed design of an access scheme for the Hunter-Central Coast REZ.
(We have tracked that page since July; our
October story sets out what the paper proposed.)
The paper also proposes where the scheme would reach. Its scope table (PDF p. 17) includes the 500, 330 and 132 kV networks in the zone and marks the “66 kV and below network” as “Excluded”. The Kurri Kurri battery would plug in by a 33 kV cable. The paper does not deal with a battery inside a zone substation, and EnergyCo has not said how it would treat one.
How we read the documents
The NSW Planning Portal’s list of projects on exhibition was read on 21 November 2026; the Kurri Kurri battery was on its second page. The project’s document list loads only in a browser, and its download links answered a plain request with “Access denied” but downloaded from the register page in a browser. We read the exhibition notice, the EIS main volume (dated 5 November 2026) in full on benefit sharing, engagement, the site and the project description, and the council’s requirements-stage letter. We searched the community and stakeholder outcomes report (Appendix F) and the social and economic impact assessment (Appendix P), which repeat the EIS on the scheme and the levy request; we did not read the other appendices. The council’s contributions page refused a plain request and was read in a browser. Arithmetic: 800 × $150 = $120,000; $120,000 × 25 = $3,000,000; 1% of $247,486,275 = $2,474,862.75; 800 ÷ 200 = 4 hours. We did not contact Ausgrid, Cessnock City Council or EnergyCo. On 21 November 2026 we asked the department what it advised on whether the Cessnock contributions plan applies to this project; we will add its answer here, or say that it has not answered.
Our read
This section is opinion, based on the facts and documents above.
Naming a rate is progress, and Berkeley Vale should get the same line. A week ago a reader of Ausgrid’s documents could not tell what its community scheme was worth. Now Kurri Kurri says $150 per MWh a year, the rate Ausgrid offered Newcastle and the state sets for rural batteries. Two EISs from the same company, a day apart, should not say different things about the same program-wide scheme.
A number is not yet a commitment. At Steel River the rate came with a term, a lump sum and a planning agreement the consent requires. At Kurri Kurri it comes with none of those, and it sits behind an access scheme that has missed its indicative date and may not reach a 33 kV battery at all. A submission asking the department to put the rate, a term, indexing and the council’s role into the conditions of consent would be asking for what Newcastle already has.
The levy question deserves a public answer. The council relied on the state’s own guideline, which says batteries on industrial land pay ordinary contributions. The EIS says the department advised on whether the levy applies but does not say what it advised. Whichever way it went, Cessnock residents should be able to read it before the exhibition closes.
Submissions
Submissions close on Thursday 17 December 2026 and go through the project’s register page (“Make a submission”), where they are published. The notice says you can ask for your name to be withheld, and that a submission must declare reportable political donations from the last two years.
We will read the agency advice on the EIS, including Cessnock City Council’s, when it is posted to the register page after the exhibition, and report what it says about the levy and the grants.