Lightsource bp, which its consultant’s report describes as a bp company, is building the Goulburn River Solar Farm at 2335 Wollara Road, Merriwa. The Department of Planning, Housing and Infrastructure approved it on 22 August 2024, as the planning minister’s delegate, and solar construction started in April 2025. The department’s exhibition notice for the second modification of that consent (SSD-33964533-Mod-2) puts it on public exhibition from 19 November until Thursday 3 December 2026.

The modification does several things at once: on-site rock crushing and concrete batching, a changed footprint, use of two emergency tracks for construction traffic, longer trucks, revised consent conditions and a construction period that more than doubles. The biggest change is the battery. The modification report, prepared by the consultancy Umwelt for Lightsource bp and dated September 2026, puts the increase from 2,060 MWh to 4,300 MWh at a 109% increase in storage capacity. (section 3.1.6, p. 39).

Goulburn River Solar Farm: approved and proposed

From the modification report’s comparison table and the modification application form.

  • Battery, stored energy2,060 MWh approved; 4,300 MWh proposed (central battery 900 to 2,400; batteries spread through the solar arrays 1,160 to 1,900)
  • Battery, power1,030 MW approved; 1,068 MW proposed
  • Export to the grid450 MW approved; 480 MW proposed
  • Construction27 months in the EIS; 60 months proposed, with the last batteries finished about the end of 2029
  • Cost$880 million capital investment at approval; an additional estimated development cost of $1,054,000,000 for this modification
  • Transformers3 approved; 4 proposed
Sources: modification report, Table 3.1 (pp. 16 to 17) and section 3.1.7 (p. 42); modification application form, p. 1; the department’s assessment report, August 2024, p. iv. Our arithmetic: 4,300 − 2,060 = 2,240 MWh added; 4,300 ÷ 2,060 = 2.09.

The report gives two reasons the battery can grow so much without more containers in the arrays: The average energy per container has approximately doubled in this time. (p. 9), and the central battery moves about 300 m west and grows from 258 to 312 containers (pp. 17 and 39). The project already has state and federal backing for its storage: a Long Term Energy Service Agreement with the NSW Government for the spread-out batteries, and Capacity Investment Scheme support from the Commonwealth for the solar farm (December 2024) and the central battery (September 2025) (p. 13).

The consent caps the batteries at 900 MWh central and 1,160 MWh spread out (conditions A6 and A7, p. 5), and adds a note that the company may seek to modify it to increase battery capacity in future. That is what this application does: it asks for the caps to become 2,400 and 1,900 MWh (report Table 3.3, p. 46). It is lodged as a single modification because, the report says, after consultation with the department this was the most efficient mechanism, and each component results in no more than a minor or reduced environmental impact compared with the Approved Project. (p. ii).

The notice and the application give different sizes

The department’s notice is what most people see first. It describes the approved battery correctly, as a combined 1,030 MW / 2,060 MWh, but describes the change as an increase in the battery to 2,060 MW / 4,500 MWhA. The application form Lightsource bp lodged says 1,068 MW / 4,300 MWh, and so do the modification report, the social impact statement, the traffic assessment and the hazard assessment. None of the other six package documents we searched uses 4,500 MWh or 2,060 MW for the battery.

Exhibit A · from the source

Department of Planning, Housing and Infrastructure exhibition notice for SSD-33964533-Mod-2: the approved development is described as a combined BESS with a total capacity of 1,030 MW / 2,060 MWh; the proposed modification as an increase in BESS to 2,060 MW / 4,500 MWh.
Page 1 of the department’s exhibition notice for the Goulburn River Solar Farm Modification (SSD-33964533-Mod-2), read 21 November 2026. Outlined: the approved battery size, and the size the notice gives for the change. The application form says 1,068 MW / 4,300 MWh. Download the notice (the link works from a browser; the register page lists it under Notice of Exhibition) · Back to the story

One smaller loose end sits in the hazard assessment (Appendix I). It models the central battery on an indicative 6.9 MWh cabinet and notes (Appendix B, p. B-2) that 312 of them come to 2,153 MWh, against the 2,400 MWh the project nominates. The assessment says the product will be confirmed at detailed design.

What the state’s rule asks for

The department’s Benefit-Sharing Guideline (November 2024) sets how much large solar, wind and battery projects should put into their communities: $850 per megawatt a year for solar, and $150 per megawatt hour a year for a stand-alone battery on rural land (section 4.1, p. 24). It is to be considered for modifications that add capacity, but only for the addition: the rates only apply to the increase in capacity and not the existing, approved capacity of the project. (p. 9). And a battery next to solar is excluded outright (p. 25): The BESS benefit-sharing rate only applies to stand-alone systems and must not be applied to a battery that is developed alongside solar and wind energy generation. The guideline’s own worked example sets the battery line at $0.

So the 2,240 MWh Lightsource bp wants to add attracts no guideline rate. Had the same storage been built as a stand-alone battery on rural land, the guideline rate would be $336,000 a year. For comparison, the Bells Mountain battery near Muswellbrook, 1,500 MWh in all, offers $225,000 a year at that rate.

The modification report does not mention the Benefit-Sharing Guideline (we searched it for “guideline”; the guidelines it cites are on solar energy and on preparing modification reports). Its impact table (Table 6.1, p. 62) says The centralised BESS will provide an additional community benefit package, which is surplus to requirements under the EP&A Act, and is being developed with feedback from UHSC and the community. UHSC is Upper Hunter Shire Council. The social impact statement (Appendix G, p. 16) is the only document that puts dollars on the packageB: Lightsource bp proposes to contribute $30,000 per annum to a First Nations Benefit Fund and $20,000 a year to the Clontarf Foundation, which the statement describes as supporting educational, employment and social programs for young Aboriginal and Torres Strait Islanders. That is $50,000 a year. The same passage mentions additional contributions to the planning agreement with the council, more grants through its existing Community Investment Programme, and that it is considering a near-neighbour benefit program, but gives no amounts for those.

Exhibit B · from the source

Goulburn River Solar Farm social impact statement addendum, section 3.3: additional contributions to the VPA with Upper Hunter Shire Council and initiatives for neighbouring landholders; increased Community Investment Programme funding; a near-neighbour benefit program under consideration; $30,000 per annum to a First Nations Benefit Fund and $20,000 per annum to the Clontarf Foundation.
Page 16 of the social impact statement addendum (Umwelt for Lightsource bp, September 2026, Appendix G to the modification report), section 3.3, BESS Capacity Increase, read 21 November 2026. Outlined: the two amounts named. Download Appendix G (the link works from a browser) · Back to the story

The existing planning agreement does not grow with storage either. The consent (condition A16, p. 6, and Appendix 3, p. 23) requires annual payments to the council at the greater of $346 per megawatt installed or $190,000, both indexed to CPI. The formula counts megawatts, not megawatt hours, so doubling the storage does not by itself change it. The report records that the agreement is in place and the first annual payment has been settled (p. 63).

Community money a year, against the storage being added

Dollars a year, not indexed. Bars to scale; the full width is $336,000.

The guideline rate, if the added 2,240 MWh were a stand-alone rural battery$336,000
Bells Mountain’s offer, on its whole 1,500 MWh$225,000
Goulburn River’s existing planning agreement floor, whole project$190,000
New money named in the modification documents$50,000
Sources: Benefit-Sharing Guideline, section 4.1 (p. 24); Bells Mountain BESS EIS, via our 11 November story; consent Appendix 3 (p. 23); social impact statement addendum, p. 16. Our arithmetic: 2,240 × $150 = $336,000; 1,500 × $150 = $225,000; $30,000 + $20,000 = $50,000. The top bar is a comparison only: the guideline says this rate must not be applied to a battery built alongside solar. The $190,000 floor is CPI-indexed and predates this modification; the documents give no figure for the extra planning agreement contributions they mention.

The road the shire was promised

The consent lists road upgrades the company must build (Appendix 4, p. 24), including the Realignment, widening and sealing of a 4.7 km unpaved section of Wollara Road. The report says that upgrade was added as a community benefit through the planning agreement, not because the project’s traffic needed it (p. 6). The modification removes 1.2 km of it, the stretch through Tongo State Forest, citing boundary and tenure problems that would need State Forest land revoked and a land swap with Crown Lands, the Forestry Corporation of NSW (the state’s forestry corporation) and a private landholder (p. 23).

Lightsource bp says it will reallocate the funding to an alternate community benefit initiative, to be agreed with the Upper Hunter Shire Council. (p. 23). The options named so far are grading or resurfacing Wollara Road, or upgrading a section of Ringwood Road. None of the documents we read says how much money is being moved: the modification report, the social impact statement, the updated project description and the traffic assessment carry no dollar figure for the road. The social impact statement (p. 15) records the cost to trust plainly: For some community members, the proposed upgrades to Wollara Road formed part of the basis for accepting Project impacts and were viewed as a key community benefit. It also says consultation found general support for spending the money on Ringwood Road instead, and that the Forestry Corporation did not object to dropping the upgrade.

How we read the documents

The NSW Planning Portal’s list of projects on exhibition was read on 21 November 2026. The modification’s document list loads only in a browser, and its downloads worked only from the register page in a browser. We read the exhibition notice, the application form, the modification report (Umwelt, September 2026) on the project changes, benefits, roads, timing and impacts, and sections 3.1 to 3.3 of the social impact statement addendum (Appendix G), and searched the updated project description (Appendix A), traffic assessment (Appendix F) and hazard assessment (Appendix I) for capacity and dollar figures. From the original approval we read the consent of 22 August 2024 and the department’s assessment report. We did not read the biodiversity, heritage, noise, bushfire or visual appendices. The report’s own figures for solar capacity differ between sections (550 MWp and 585 MWp for the approved project), so we have used only its export figures. Arithmetic: 4,300 − 2,060 = 2,240 MWh; 4,300 ÷ 2,060 = 2.09; 2,240 × $150 = $336,000; 1,500 × $150 = $225,000; $30,000 + $20,000 = $50,000; 60 − 27 = 33 months. We asked Lightsource bp on 22 November how much funding it would reallocate from the 1.2 km Wollara Road section, and will publish its answer here. We did not contact Umwelt or Upper Hunter Shire Council. On 21 November 2026 we asked the department which battery size, the notice’s or the application’s, describes the proposal on exhibition; we will add its answer here, or say that it has not answered.

Our read

This section is opinion, based on the facts and documents above.

This is not a tweak. The modification is costed at more than the whole project’s capital investment when it was approved, and it doubles the storage on site. The law lets it go through as a modification if it is substantially the same development, and the department will judge that. But two weeks is a short window for a change of this size, and readers deserve to see it described accurately on the notice that opens it.

The guideline has a gap the size of a big battery. Excluding batteries built beside solar made sense when they were a small add-on. Here the storage being added is bigger than the whole Bells Mountain battery, which pays $225,000 a year to its community, and the rule sets its rate at $0. That is a gap in the rule, not a fault of the applicant, which is offering something the rule does not require.

The road money is the benefit with no number. A promise to the shire is being swapped for an initiative still to be agreed, and nothing on exhibition says how much is being moved, so a reader cannot weigh the swap from the documents. Residents who used that upgrade to accept the project have until 3 December to say so.

Submissions

Submissions close on Thursday 3 December 2026 and go through the modification’s register page (“Make a submission”), where they are published. The notice says you can ask for your name to be withheld, and that a submission must declare reportable political donations from the last two years.

We will read the agency advice, including Upper Hunter Shire Council’s, when it is posted to the register page after the exhibition, and report what it says about the road money and the added storage.