The station is the 660 MW gas peaker at Hart Road, Loxford, near Kurri Kurri, that Snowy Hydro has been commissioning since 2025. It runs under Environment Protection Licence 21627. When we wrote about its diesel testing in July, the EPA’s register was mid-migration and the licence page would not open, so we said we would check again when the new register was live. It now is, and the licence carries 21 notices. The ones that matter are a section 96 prevention notice, three variations of it, and two licence variations made for the commissioning.
What happened in July 2025, by the EPA’s account
Prevention notice 3513435, dated 21 August 2025, sets out the sequence (pp. 3 and 4). Snowy Hydro told the EPA on 20 June 2025 that it would start commissioning the first turbine, GT1. On 8 July 2025 the EPA’s Environment Line received about 13 reports of visible or odorous emissions, and on 9 July about 38. The notice records some callers describing “thick black” and “brown” smoke and a diesel smell, and some alleging health effects such as burning eyes and throat irritation. An EPA officer saw a visible plume on 9 July. Snowy Hydro told the EPA it had started first fire-up on diesel on 8 July, and called on the afternoon of 9 July to say diesel commissioning had stopped.
The notice quotes Snowy Hydro’s own explanation, from an update on its website on 18 July
2025:
The level of emissions and odour was not expected and was associated with starting up a brand new generator, combined with strong winds
.
It also quotes the company’s report to the EPA: the turbine was running at “full speed, no
load” on diesel, and during the tests
evidence of a malfunction of the CEMS unit was observed
,
the continuous emissions monitor on the stack. Once that could not be fixed, the company said,
commissioning stopped.
On that record the EPA wrote (p. 1) that it
reasonably suspects that an activity has been or is being carried on in an environmentally unsatisfactory manner
at the station. It names (p. 6) two possible breaches of the Protection of the Environment
Operations Act, each as a “potential contravention”: section 124, on operating plant in a
proper and efficient manner, and section 129(1), on offensive odour. A prevention notice directs the
occupier to do things differently in future. It is not a penalty, and no court has made any finding.
What the notice required, and how it changed
The directions (pp. 6 to 8) were: start and stop both turbines on gas, not diesel, during diesel commissioning wherever the Australian Energy Market Operator’s testing allows; install a continuous particulate monitor on the stack being tested; and, before any more diesel testing, give the EPA a Diesel Commissioning Environmental Management Plan with stack and community air monitoring, “trigger action response plans” that include triggers to stop testing, and a community engagement plan. The triggers had to take account of community complaints.
The EPA varied the notice twice in September 2025, and each variation records a problem on Snowy Hydro’s side:
- 19 September (3513794). The particulate monitor had worked, recording a highest reading of 6.3 mg/m³ against the 50 mg/m³ regulation limit, but had then stopped working, and Snowy Hydro could not get another before the end of September. The EPA let it finish GT1’s diesel program, scheduled for 16 to 24 September 2025, without one, and required one on the second turbine, GT2, before its diesel testing (pp. 2 and 3).
- 29 September (3513913). Starting GT1 on gas and switching to diesel, as the
notice required, had caused a number of trips at the fuel changeover, and the company thought the
combustors might be coated with carbon blocking the diesel injectors (p. 2). The EPA allowed
start-up on diesel
as otherwise agreed to beforehand in writing by the EPA
(p. 3).
Before the 2026 diesel runs
The 2025 commissioning exemption expired on 31 December 2025, and a December variation (1655217,
p. 1) says the EPA understood commissioning was likely to continue into 2026
.
Snowy Hydro asked for a new exemption on 27 November 2025. Licence variation 1658051 of 1 May 2026
records that the EPA asked for more air modelling because, after July 2025, it considered the first
modelling did not appropriately address potential impacts from FSNL operational conditions
(p. 3).
The EPA Board approved a new exemption on 23 April 2026, published on 1 May and running until
11.59 pm on 30 April 2027 (p. 4). The same notice says, of the July 2025 event (p. 3):
The EPA is investigating the event and has issued Prevention Notice no. 3513435 to increase regulatory oversight of the activities.NSW EPA, notice of variation of licence 21627, no. 1658051, 1 May 2026, paragraph L A
Exhibit A · from the source
Then on 15 July 2026, the day before Snowy Hydro’s overnight diesel testing was due to start
(on or after 16 July), the EPA issued a third variation, VN-2431. It records (pp. 2 and 3) that on 10 July 2026 it had received
confirmation of a working particulate monitor and the updated plan and triggers, that the earlier
actions had now been completed to the satisfaction of the EPA
,
and that Snowy Hydro had put ten further measures in place. Among them:
- no more full-speed-no-load testing on GT1;
Diesel FSNL testing on GT2 will occur in runs of less than two hours in the middle of the night to reduce potential impacts on the community
;- no such testing in early-morning inversions with light north-westerly winds blowing toward the nearest homes;
- air monitoring and odour surveys in the community during all diesel testing; and
An independent arbiter will be appointed to be present on site during each commissioning activity to observe air quality monitoring outputs. This person will have full authority to take actions, up to and including halting operations, if TARP triggers are met.
That is consistent with what Snowy Hydro’s community page told residents in July: overnight testing, one generator at a time. The consolidated directions (pp. 3 and 4) now also require real-time monitoring of smoke from the stack.
What the licence allows, in normal running and in commissioning
Stack concentration limits from Environment Protection Licence 21627 (version of 10 June 2026), in mg/m³ at the licence’s reference conditions.
- Normal, on gas (L3.2)Nitrogen oxides 51; carbon monoxide 12.5
- Normal, on diesel (L3.4)Nitrogen oxides 86; carbon monoxide 63
- Commissioning, to 30 April 2027 (E2.4)Nitrogen oxides 103 on gas, 123 on diesel; solid particles 85; smoke 60% opacity
- Hours (L7.1, L7.2)No more than 1,100 hours a year generating, of which no more than 175 on diesel, unless AEMO directs it to run
The diesel cap is new to our reporting. Snowy Hydro’s page cites the 1,100-hour approval, but
the licence also says (p. 15) that fuel-burning equipment
must not be fired on diesel for the purpose of generating electrical power at the premises for more than 175 cumulative hours per calendar year.
What Snowy Hydro reported
Licensees report their own non-compliances in an annual return. For the licence year 31 January 2025 to 30 January 2026, the register shows a return dated 31 March 2026 with three entries: an exceedance of the carbon monoxide and nitrogen oxides limits under condition L3.2 at the GT2 stack during GT2’s commissioning, once; a carbon monoxide exceedance at the same stack, also during GT2’s commissioning, once; and the visible plume and odours from the GT1 stack during first-fire diesel commissioning on 8 and 9 July 2025, twice. In that third row the column that normally holds the licence condition number shows instead a note that is cut off on the register after “The EPA is investiga”. The three earlier licence years recorded no non-compliance.
What the register does not say
It records no outcome of the EPA’s investigation. The notices listed against the licence are
licence variations, the 2025 exemption, the prevention notice and its three variations; there is no
later notice. The EPA’s
policy
on investigations says it does not usually comment on a current one, and
Where an investigation is made public, we will usually make a statement at the conclusion of the investigation to report on the outcome.
Nor does it say whether diesel commissioning is now complete. Condition E2.6 (p. 29) requires Snowy Hydro to tell the EPA within two days of finishing commissioning on each turbine, and E2.7 to give it an emissions report within four weeks. Neither is published on the register.
Snowy Hydro’s community page has said since at least July 2026 that
The impacts of our recent testing is currently under investigation and we will communicate as required in due course.
The page does not say who is investigating, and the EPA’s documents do not refer to it. We are
not treating the two as the same investigation.
How we read the documents
The old register address, apps.epa.nsw.gov.au/prpoeoapp/, now redirects to the EPA’s new register. We searched licence number 21627, read its summary, all three pages of its notices list (21 notices back to May 2022), its applications and its compliance reporting, and downloaded and read in full the prevention notice (9 pages), its three variations (5, 4 and 6 pages), the licence variations of June 2025, December 2025, May 2026 and June 2026, and the current licence (version 17, 34 pages). The register gives the documents no fixed web address: to find them, search licence 21627 and open each notice number. Page numbers are as printed on each document. The report counts are the notice’s own, which it gives as approximate. Snowy Hydro’s community page was read on 23 November 2026. The NSW EPA is the state’s environmental regulator; Snowy Hydro is the licence holder and operator of the station; the Australian Energy Market Operator runs the electricity market and sets the tests a new generator must pass.
Our read
This section is opinion, based on the facts and documents above.
The regulator’s file is the fullest public account of what happened. Since July we have quoted one unexplained sentence about an investigation. The EPA’s documents set out the July 2025 event, its own suspicion, the monitoring that failed, the problems that followed, and the conditions that were in force when diesel testing resumed in 2026. The documents do not show anyone has been found to have broken the law, and readers should not take them that way. They do show that the 2026 testing ran under much tighter rules than the 2025 testing did, and that is worth knowing if you live nearby.
Residents should not need the register to learn this. Snowy Hydro’s page, asked what air monitoring has been agreed, points to the licence’s routine stack-monitoring table, Figure M2.2. The commissioning measures, including the particulate monitor, the community air and odour monitoring and the independent arbiter, are in condition E2 and the EPA’s notices, and the page does not mention them. If there is more diesel testing before April 2027, they are the commitments to hold it to, and the operator’s own page is where its neighbours look. We asked Snowy Hydro on 23 November whether diesel commissioning is complete on both turbines, and if not, whether its page will set those measures out.
The investigation should end with a public word. The EPA confirmed in a public notice that it is investigating, and its own policy says it usually reports the outcome of a public investigation. We asked the EPA on 23 November whether the investigation has concluded and, if so, what it found.
What we will check
We will add the answers from Snowy Hydro and the EPA here, or say that they have not answered. We will read the register again for any new notice on licence 21627 and for the 2026-27 annual return, and report the outcome of the EPA’s investigation when the EPA publishes it.